Components of Runoff & the Hydrograph

Rainfall−Abstraction from PPT=Runoff

Total runoff from the catchment is divided into 4 groups:

  1. PPT over the stream channel
  2. Surface runoff — (i) overland flow, (ii) channel flow
  3. Interflow
  4. Ground water flow

Hydrograph

In this chapter, our study of hydrograph would be short-term hydrograph, called flood hydrograph, which is used for flood control, flood forecasting, and determination of design discharge for hydraulic structures. A hydrograph involves in itself the combined effect of rainfall and catchment characteristics.

Q (hyetograph) Direct runoff Base flow t →

Hydrograph — a rainfall hyetograph produces direct runoff, riding on top of a slowly varying base flow.

The discharge noted in the flood hydrograph can be divided into:

  1. Direct runoff — includes (i) PPT over the stream channel, (ii) surface runoff, (iii) prompt interflow.
  2. Base flow — includes (i) ground water flow, (ii) delayed interflow.
Q Direct runoff hydrograph (DRH) t →

A direct-runoff hydrograph (DRH) does not include base flow.

Isolated Storm & Complex Storm Hydrograph

If two storms occur in a catchment such that the second does not start until the effect of the first has completely ceased (base flow started), the hydrograph so obtained is called an isolated storm hydrograph, and this would generally be a single-peak hydrograph.

Note Depending upon the catchment shape, isolated storms may lead to a multiple-peak hydrograph.

If, however, the second storm starts before the effect of the first storm has ceased, the resulting hydrograph is called a complex storm hydrograph. In hydrological analysis, we generally use an isolated storm hydrograph having a single peak.

Components of a Hydrograph

Q A B C D E tₛᵢ Base period

A — starting point; AB — rising limb; BCD — crest segment; B, D — points of inflection; DE — recession limb; E — end point. tpk is measured from the CG of the hyetograph to the peak C; the base period spans A to E.

Essential components of a hydrograph:

  1. Rising limb — mainly depends on the duration, intensity, and distribution of rainfall, and to a lesser extent on the catchment characteristics.
  2. Crest segment — includes the peak discharge, and is marked by the inflection points at the start and end. The point of inflection at the end of the segment is assumed to represent the time at which overland flow has ceased; at this time storage in the catchment is maximum, and thereafter depletion occurs.
  3. Recession limb — independent of storm characteristics, and mainly depends upon the catchment characteristics.

Factors Affecting the Flood Hydrograph

(a) Shape of catchment — a fan-shaped catchment produces a broad, gently rising hydrograph; a fern/leaf-shaped catchment (narrow, elongated) produces a sharper, quicker peak; a catchment shaped so runoff arrives in two pulses produces a multi-peak hydrograph.

(b) Size of catchment — in small catchments, overland flow is more predominant, and in large catchments, channel flow is more predominant. Thus in a small catchment the effect of land use and intensity of rainfall will be more predominant, and in a large catchment, the effect of drainage density will be more predominant. The time base of a large catchment is generally longer as compared to a small catchment.

(c) Drain slope — if the drain slope is large, the peak will come early and the time base will be small.

(d) Intensity of rainfall — if the intensity of rainfall is more, then for a given duration of rainfall, the peak will be high.

(e) Distribution of rainfall — isochrones are lines joining points from where the water particle takes the same time to reach the catchment outlet. When rainfall occurs closer to the outlet, the peak will come early and it will be large, as compared to the situation when rainfall occurs in an area away from the outlet.

5hr 4hr 3hr 2hr 1hr isochrones

Isochrones drawn as contours of equal travel-time to the catchment outlet.

(f) Time of concentration (tc) — the time taken by a water particle to reach the catchment outlet from the remotest point. If the rainfall duration is greater than or equal to the time of concentration, the intensity of runoff is maximum at the outlet.

constant intensity, infinite time — hyetograph S-curve tᵼ max intensity (cm/hr) tᵼ duration (hr)

Left: intensity–duration curve, with icr occurring at tc. Right: a rainfall of constant intensity applied over infinite time produces an S-curve that levels off at tc.

Hydrograph Separation

Separation of base flow from the flood hydrograph (total storm hydrograph) is called hydrograph separation.

Flood hydrograph=DRH+Base flow
A E N days

Simplest separation: a straight line from the point where the rising limb departs from base flow (A) to the point on the recession limb N days after the peak (E).

N=0.83A0.2
N — days from peak to point E
A — area of catchment, in km²
A C E freehand linear → Runoff

More refined separation: a freehand curve from A that dips under the crest before rejoining the linear-to-E segment near the point of inflection C.

Effective Rainfall Hyetograph (ERH)

When the initial losses and infiltration losses are subtracted from the rainfall hyetograph, we get the effective rainfall hyetograph (ERH). It is also called the hyetograph of rainfall excess or supra rainfall.

Area under ERH×Catchment area=Area under DRH
Worked Example

The flood data and base flow in a stream is estimated for a catchment area of 600 km². Estimate the rainfall excess, in cm.

Time (days)0123456789Σ
Discharge (m³/s)2063151133906344292030643
Base flow (m³/s)20222528262321202020225
DRH (m³/s)041126105644013900
Runoff=643−225 m³/s=418 m³/s

Area under DRH, by the trapezoidal rule with 1-day spacing:

Area=12×41×1+1241+126×1+…+129+01 =Q1+Q2+…+Q9×1=408 m³/sec × 1 day =408×3600×24 m³=35.25×106 m³

Rainfall excess = QV/A:

Rainfall excess=QVA=35.25×106600×106 m

Rainfall excess = 5.87 cm

Worked Example

A storm over a catchment of area 5 km² has a duration of 14 hr, and a mass curve of rainfall is as given below. If the φ-index of the catchment is 0.4 cm/hr, determine the ERH and the volume of direct runoff from the catchment due to the storm.

Time (hr)02468101214
Accumulated rainfall (cm)00.62.85.26.77.59.29.6
Individual (cm)—0.62.22.41.50.81.70.4
Hourly (cm/hr)—0.31.11.20.750.40.850.2
ERH (cm/hr)—00.70.80.3500.450

With catchment area 5 km² = 5×10² ha, volume of direct runoff over the four 2-hr intervals with positive ERH:

Volume=0.7+0.8+0.35+0.45 cm/hr×Area =2.3×10−2 m/hr×2hr×5×102 ha

Volume = 23 ha·m

Unit Hydrograph

Q 1/D cm/hr D hr D-hr unit hydrograph t →

A D-hr unit hydrograph corresponds to 1 cm of effective rainfall applied uniformly at rate 1/D cm/hr over D hours.

The unit hydrograph of a catchment is defined as the hydrograph of direct runoff (DRH) resulting from 1 cm of effective rainfall depth applied uniformly over the catchment area at a uniform rate (intensity), during a specified period of D hr. Thus the intensity of rainfall for a D-hr unit hydrograph is 1/D cm/hr.

D should not be more than: (a) time of concentration tc, (b) lag time tL, (c) period of rise.

Assumptions of Unit Hydrograph

  1. Effective rainfall should be uniformly distributed over the catchment basin.
  2. Effective rainfall is constant over the catchment during the unit time, i.e. intensity is constant.
  3. Time invariance — the direct-runoff hydrograph for a given effective rainfall over a catchment is always the same, irrespective of when it occurs. Hence, any previous rainfall is not considered to affect the new rainfall.
    Note Antecedent PPT is otherwise important because of its effect on soil infiltration rate, depressional and detention storage, and hence on the resultant hydrograph.
  4. Linear response — the ordinate of DRH is directly proportional to the effective rainfall hyetograph ordinate. If effective rainfall is K cm instead of 1 cm (same D-hr duration), all ordinates scale by K, and the time base TB remains the same.
Note The assumption of linear response enables us to use the principle of superposition: if two rainfalls of D-hr duration and magnitude M₁ and M₂ cm occur successively, the combined DRH for the two storms can be determined by multiplying the ordinates of the D-hr unit hydrograph first by M₁ and then by M₂, to obtain two DRHs, and adding the ordinates of the two after lagging the ordinate of the second DRH by D hr.
Worked Example — Combining Two Storms by Superposition

φ-index = 1 cm/hr. Ordinates of 2-hr and 4-hr unit hydrographs are given below. Draw the DRH for a hyetograph of 3 cm/hr (0–2 hr) and 4 cm/hr (2–6 hr).

ERH: 0–2 hr at (3−1) = 2 cm excess (over the 2-hr UH), 2–6 hr at (4−1) = 3 cm excess over 4 hr (over the 4-hr UH).

Time (hr)024681012141618202224
2-hr UH013581211107620
4-hr UH027101218201816141053
2×(2-hr UH)04122032484440282480
3×(4-hr UH), lag 2hr—0248412014421624021619216812060
DRH combined043610415219226028024421617612060

(Continuing to the tail: 26 hr→96, 28 hr→60, 30 hr→36, 32 hr→12, 34 hr→0.)

DRH=UH×effective rainfall
Q time (hr) Resultant DRH

Resultant combined DRH, peaking near 280 m³/s around t = 14 hr.

Worked Example — Adding a Rising Base Flow

In the above problem, if the base flow is constant up to 16 hr = 30, and thereafter increases by 4 units every 2 hr till the end of 32 hr, calculate the ordinates of the flood hydrograph.

Time (hr)02468101214161820222426283032
Base flow3030303030303030303438424650545862
Resultant DRH0436104152192260280244216176120966036120
Flood hydrograph303466134182222290310274250214162142110907062
Note If 3 unit hydrographs of D-hr duration, each having time base TB, are superimposed to find the DRH for three consecutive rainfalls of D-hr duration, then the resultant DRH will have a time base of TB + 2D.

Derivation of a UH from a Complex-Storm DRH

Given the ERH as three successive D-hr rainfalls R₁, R₂, R₃ and the resulting composite DRH ordinates x₁…x₈, the D-hr UH ordinates a, b, c, d, e can be recovered by successive elimination:

TimeDRH ordinateR₁×D-hr UHR₂×D-hr UH (lag D)R₃×D-hr UH (lag 2D)DRH (by UH)
000000
Dx₁R₁a00R₁a
2Dx₂R₁bR₂a0R₁b + R₂a
3Dx₃R₁cR₂bR₃aR₁c + R₂b + R₃a
4Dx₄R₁dR₂cR₃bR₁d + R₂c + R₃b
5Dx₅R₁eR₂dR₃cR₁e + R₂d + R₃c
6Dx₆0R₂eR₃dR₂e + R₃d
7Dx₇00R₃eR₃e
8D00000

Solving in order: x₁ = R₁a ⇒ a; x₂ = R₁b + R₂a ⇒ b; x₃ = R₁c + R₂b + R₃a ⇒ c; x₇ = R₃e ⇒ e; x₆ = R₂e + R₃d ⇒ d — hence find a, b, c, d, e in that order.

Worked Example

Stream flow due to three successive storms of 2.9, 4.9, and 3.9 cm of 6-hr duration each on a basin are given below. Area of catchment is 118.8 km². Assuming a constant base flow of 20 m³/sec, derive a 6-hr UH for the basin. An avg storm loss of 0.15 cm/hr (φ) can be assumed.

Time (hr)03691215182124273033
Q (m³/s)20509214019920220414484.545.52920
DRH (m³/s)0307212017918218412464.525.590

Effective rainfall (φ = 0.15 cm/hr over 6-hr blocks): 2.9−0.9 = 2 cm, 4.9−0.9 = 4 cm, 3.9−0.9 = 3 cm.

Time base of UH = 33 − 2×6 = 33 − 12 = 21 hr. Solving successively from the DRH table (labelling the 6-hr UH ordinates a…f at t = 3, 6, 9, 12, 15, 18 hr):

30=2a  ⇒  a=15 72=2b  ⇒  b=36 120=2c+4×15  ⇒  c=30 179=2d+4×36  ⇒  d=17.5 9=3f  ⇒  f=3 25.5=3e  ⇒  e=8.5

6-hr UH ordinates: 0, 15, 36, 30, 17.5, 8.5, 3, 0 m³/s at t = 0, 3, 6, 9, 12, 15, 18, 21 hr

UH of a Different Duration

Given a D-hr UH, to find a T-hr UH where T = mD:

  1. m is an integer — take m copies of the D-hr UH, each lagged by D hr, and sum the ordinates at each time to get the DRH for m cm of rainfall occurring uniformly over mD hr. Dividing this DRH's ordinates by m gives the mD-duration (T-hr) UH.
  2. m is not an integer (fraction) — use the S-curve technique (also usable for case (a)).
20 hr UH D-hr UH D-hr UH lag D DRH of 2cm effective rainfall in 20hr

Case (a), m = 2: summing a D-hr UH with itself lagged by D hr gives the DRH for 2 cm over 2D hr; dividing by 2 gives the 2D-hr UH.

Worked Example

From the 2-hr UH, obtain the 6-hr UH. Ordinates of the 2-hr UH are given below.

Time (hr)024681012141618202224
2-hr UH05252520151310820
lag 2hr—05152520151310820
lag 4hr——05152520151310820
3cm DRH, 6hr lag0520456060483831201020
6-hr UH (÷3)01.676.671520201612.6710.336.673.330.670

S-Curve

When the new hydrograph duration is not an integral multiple of the D-hr UH, we use the concept of the S-curve.

The S-curve is defined as the hydrograph of direct runoff resulting from a continuous effective rainfall of uniform intensity (1/D) cm/hr, applied forever. It is constructed by adding together a series of D-hr UH, each lagged by D hr. The S-curve attains a constant ordinate, called the equilibrium discharge, approximately at the end of the base period of the first unit hydrograph.

1/D cm/hr, D D D D D … → ∞ Q Qᴸᴸᴱ = A×(1/D) = A/D D-hr S-curve D-hr UH, all lagged by D hr

S-curve built from repeated D-hr UH, each lagged D hr, summing to a constant equilibrium ordinate Qmax = A/D.

If we consider two S-curves of D-hr each, lagged by T hr, the difference of the two S-curve ordinates gives the DRH of T-hr rainfall of magnitude (T/D) cm. To obtain the T-hr UH, the (S₁−S₂) ordinate is divided by (T/D):

1 cm, T-hr UH=S1−S2T/D
Worked Example

Ordinates of a 4-hr UH for a particular basin are given. Derive the S-curve and the 2-hr UH. Also calculate the maximum ordinate of the S-curve, taking catchment area = 630 km².

Time (hr)0246810121416182022242628
4-hr UH02510016019017011070302061.50
SA (cumulative)025100185290355400425430445446.5446.5446.5446.5436
SB (SA lag 2hr)0025100185290355400425430445446.5446.5446.5436
SA−SB (2cm DRH)02575851056545255151.50000
2-hr UH (÷2)0501501702101309050103030000
Handwriting noteThe SA/SB tail values on this page have a couple of overwritten corrections (e.g. entries crossed and rewritten near t = 24–28 hr) that don't fully reconcile with a strictly monotonic cumulative S-curve; the equilibrium value is clearly 446.5, and the table above reproduces the source's own final digits. The resulting 2-hr UH has small end-of-tail negative/irregular values in the raw source (smoothed here to 0), consistent with the source's own note that “curve should be smoothen at last.”

Take TB = 24 hr for the 4-hr UH ⇒ TB = 24 − 2 = 22 hr for the 2-hr UH. Peak ordinate of the S-curve:

Peak ordinate=14 cm/hr×630 km²=157.5×106×10−2 m³/hr

Peak ordinate of S-curve = 1.575 Mm³/hr

Advantages of UH

  1. To find the flood hydrograph, which in turn is used to find out the design discharge for hydraulic structures.
  2. Flood hydrographs can also be used for flood forecasting and warning systems.

Limitations of UH

  1. UH cannot be used for a catchment greater than 5000 km², because there will not be uniform distribution of rainfall over a large catchment area.
  2. If a large catchment has a big pond, it will affect the linear response relationship.
  3. UH theory also cannot be used for a catchment area less than 2 km² (200 ha).

Distribution Graph & Synthetic Unit Hydrograph

Distribution Graph

1/D cm/hr Ai % area of strip (% volume of direct runoff)

A distribution graph is basically a D-hr UH with ordinates showing the % of surface runoff occurring in successive D-hr intervals. Duration D is taken as the unit interval; summation of the ordinates equals 100.

Worked Example

On a catchment of 200 ha, rainfalls of 7.5 cm, 2 cm, and 5 cm occurred on three consecutive days. The avg φ-index was 2.5 cm/day. The distribution graph (% of surface runoff, extended over 6 days for every rainfall of such magnitude) is 5, 15, 40, 25, 10, 5. Determine the ordinates of the discharge hydrograph, and also determine the peak discharge. Neglect base flow.

Effective rainfall per day: day1 = 7.5−2.5 = 5 cm; day2 = 2−2.5 < 0 ⇒ 0 cm (no excess); day3 = 5−2.5 = 2.5 cm.

Time (day)Dist. graph (%)5cm DRH%2.5cm DRH% (lag 2day)Σ DRH%Vol (ha·m)Avg ord. (m³/s)
0525—250.50.057
11575—751.50.174
24020012.5212.54.250.492
32512537.5162.53.250.376
410501001503.00.347
552562.587.51.750.203
6——25250.50.058
7——12.512.50.250.029

Volume for each row = (%DRH/100) × (2 ha·m/100 × effective rainfall depth); e.g. row 0: 25% of the 5 cm rainfall over 200 ha = 0.25×5×2 ha·m = 0.5 ha·m. Average ordinate = volume ÷ (1 day in seconds), e.g. 0.5×10&sup4; m³ ÷ (3600×24) = 0.057 m³/s.

Peak discharge ≈ 0.492 m³/s at t = 2 days

Synthetic Unit Hydrograph (Snyder's Method)

A synthetic UH is obtained for an ungauged catchment (no rain gauges), usually by relating certain catchment characteristics with the UH shape. Once this relationship is available for a catchment having sufficient data, the same relationship can be applied to the UH for an ungauged catchment in the same hydrometeorologically homogeneous area. This UH is called the Synthetic UH (S-UH).

Snyder selected 3 parameters for generating the S-UH: (a) base width T, (b) peak discharge Qpk, (c) lag time tp.

L CG Lᵩᴰ

L — catchment length from the catchment divide to the outlet; LCA — distance from the CG of the catchment to the outlet.

(a)  T=72+3tp  (T, tp in hr) (b)  Qpk=2.78CpAtp  (Qpk in m³/s, A in km², Cp ∈ (0.56, 0.69)) (c)  tp=CtL·LCA0.3
Ct — represents the slope of catchment and land use; 1.35 < Ct < 1.65, but normally Ct = 1.5 is adopted
L — catchment length from catchment divide to outlet, in km
LCA — distance of CG of catchment to outlet, in km
tᵣ → Qᴸᴸ tᴱ/2 tᵣ T

Lag time tp is measured from the mid-point of the (tr-hr) rainfall to the peak Qpk.

tr=tp5.5

The UH given by the above formulas is a UH of tr hr duration. If a synthetic UH of another duration D′ hr is to be obtained, the corresponding lag tpr is given by:

tpr=tp+D′−tr4

Use tpr instead of tp in formulas (a) and (b) — when the modified tpr is put into the equations for T and Qpk, we obtain T and Qpk for the D′-hr S-UH.

To draw a smooth S-UH, we use the formula for the width of the S-UH at 75% and 50% of the peak discharge:

Qpk 0.75Qpk W75 0.50Qpk W50

Width of the S-UH at 75% and 50% of peak discharge.

W75=3.35QpkA1.08 (hrs) W50=5.85QpkA1.08 (hrs),   W50W75=1.746

Qpk in m³/s, A in km².

Worked Example

Derive the 3-hr S-UH for a catchment having area 2500 km². Length of the main stream is 120 km. Distance from the CG of the catchment to the gauging station is 80 km. Take Ct = 1.5, Cp = 0.6. Use Snyder's method.

tp=CtL·LCA0.3=1.5120×800.3=23.48 hr tr=tp5.5=4.269 hr tpr=tp+D′−tr4=23.48+3−4.2694=23.166 hr Qpk=2.78×0.6×250023.166=180.005 m³/s T=72+3×23.166=141.49 hr W75=3.35180.00525001.08=57.42 hr,   W50=1.746W75=100.266 hr

tpr = 23.166 hr, Qpk = 180 m³/s, T = 141.49 hr, W₁₀₀ = 57.42 hr, W₅₀ = 100.27 hr

Worked Example — Transferring an S-UH Between Catchments

Two catchments X and Y are considered to be meteorologically homogeneous. Characteristics: X — L = 50 km, LCA = 30 km, A = 500 km²; Y — L = 80 km, LCA = 60 km, A = 1000 km². For catchment X, the UH developed is of 2-hr duration, peak discharge 80 m³/s, time of peak from the beginning of rainfall is 13 hr. Find the S-UH for catchment Y.

tpr for X = 13 − 2/2 = 12 hr (peak time measured from mid-point of the 2-hr rainfall). Since D′ = 2 hr may not equal tr for X, first back-calculate tp and Ct, Cp for X:

12=tp+2−tp/5.54  ⇒  tp=12.05 hr 12.05=Ct50×300.3  ⇒  Ct=1.34 80=2.78×500×Cp12  ⇒  Cp=0.69

Applying the same Ct, Cp to catchment Y:

tp=1.3480×600.3=17.04 hr Qpk=2.78×0.69×100017.04=112.57 m³/s T=72+3×17.04=123.12 hr W75=35.44 hr,   W50=1.746W75=61.88 hr
Note The duration given in the question for the SUH on catchment X cannot be assumed to be tr hr — it is actually a different-duration SUH (of D′ hr). While calculating Cp in the expression for Qpk, use tpr, because that Qpk corresponds to tpr and not tp.

For catchment Y: tp = 17.04 hr, Qpk = 112.57 m³/s, T = 123.12 hr

Triangular Unit Hydrograph

Worked Example

A 1-hr triangular UH of a watershed has a peak discharge of 60 m³/s @ the 10th hr, and time base of 30 hr. The φ-index is 0.4 cm/hr, and base flow is 15 m³/s. (a) Calculate the catchment area of the watershed. (b) If there is rainfall of 5.4 cm in 1 hr, find the ordinate of the flood hydrograph @ the 15th hr.

(a) Area under the triangular UH = 1 cm of runoff over the catchment:

Area=12×30hr×60 m³/s=900 m³/s·hr×3600 s/hr

Catchment area = 324 km²

(b) Effective rainfall = 5.4 − 0.4 = 5 cm; the flood-hydrograph ordinate at the 15th hr (5 hr past the UH peak, on the receding limb) scales as (300/20)×15 × 5 (interpolating the triangular UH ordinate at t=15 and scaling by 5 cm):

225=30020×15 Flood ordinate=225+15

Flood hydrograph ordinate @ 15th hr = 240 m³/s

Instantaneous Unit Hydrograph (IUH)

A UH of infinitesimal duration is called the instantaneous unit hydrograph (IUH). It is mainly used when the intensity of rainfall is continuously varying, because in this case we need to divide the rainfall into very small durations and find out the response of each on the runoff.

The main advantage of IUH is that it is independent of the duration of ERH. IUH is thus independent of the rainfall characteristics, and is indicative of the catchment characteristics only.

ut=dSi·dt

IUH can be obtained approximately using an S-curve, where the ordinate of IUH at any time t (u(t)) is the slope of the 1-hr S-curve (i = 1 cm/hr). We generally use the Nash model and the Clark model to obtain the IUH.