CPM / Resource Management

Resource Allocation

Converted from handwritten notes — CPM 7 Resource Allocation.pdf, page 1

Doc No.CPM-07
StatusDraft — Awaiting Review
Converted22-07-2026
Approved—

Resource Smoothening

Reschedules activities that have float so resource demand becomes more uniform over the project — without changing the overall project duration.

In simple words You're not fighting a shortage here — you just want a smoother, less spiky demand for labour/equipment week to week. Only non-critical activities (the ones with float) get shuffled; the finish date never moves.

Resource Levelling

Reschedules activities so that maximum resource demand never exceeds what's actually available — the opposite problem from smoothening.

In simple words Here you genuinely don't have enough resource to run everything as originally scheduled, so something has to give — usually the finish date. Because activities move, the critical path itself can shift to a different chain of activities.

Smoothening vs. Levelling — quick comparison

Resource SmootheningResource Levelling
Resource availabilityUnlimited (assumed)Limited (real constraint)
Project durationUnchangedMay increase
Critical pathStays the sameMay change
GoalEven out demandStay within supply