CPM / Resource Management
Resource Allocation
Converted from handwritten notes — CPM 7 Resource Allocation.pdf, page 1
Doc No.CPM-07
StatusDraft — Awaiting Review
Converted22-07-2026
Approved—
Resource Smoothening
Reschedules activities that have float so resource demand becomes more uniform over the project — without changing the overall project duration.
- Assumes resources are unlimited
- Project duration does not change
- Critical path remains the same
In simple words
You're not fighting a shortage here — you just want a smoother, less spiky demand for labour/equipment week to week. Only non-critical activities (the ones with float) get shuffled; the finish date never moves.
Resource Levelling
Reschedules activities so that maximum resource demand never exceeds what's actually available — the opposite problem from smoothening.
- Resources are limited (a real constraint, not unlimited)
- Project duration might change — often gets pushed out
- Critical path may change as a result
In simple words
Here you genuinely don't have enough resource to run everything as originally scheduled, so something has to give — usually the finish date. Because activities move, the critical path itself can shift to a different chain of activities.
Smoothening vs. Levelling — quick comparison
| Resource Smoothening | Resource Levelling |
| Resource availability | Unlimited (assumed) | Limited (real constraint) |
| Project duration | Unchanged | May increase |
| Critical path | Stays the same | May change |
| Goal | Even out demand | Stay within supply |