CPM / Project Updating

Network Updating

Converted from handwritten notes — S:\GATE CE\OCR Tool Test\CPM_6_Updating, pages 1-5

Doc No.CPM-06
StatusDraft — Awaiting Review
Converted27-07-2026
Approved—

Introduction to Updating

Updating is a process which involves comparison between actual execution and original plan at regular intervals. If it requires, necessary actions are taken to get things back on schedule. Hence, it requires an upward flow of information.

Data Required for Updating

To perform updating of a network, the following information must be collected:

Updating Template: Below is a typical layout of the data collection table used during updating:

Activity Completed? (Y/N) If Yes: Actual Completion Time If In Progress: Remaining Duration If Yet to Start: Estimated Duration
—————
—————
—————

When to Update & Frequency

Updating is done whenever there is a major change in the duration of any activity. The frequency of updating depends heavily on the scale of the project:

Important Points during Updating

Solved Example

Problem Statement: The figure below shows the network diagram of a project, which is to be updated at the end of 12 days. The following conditions exist at the time of updating:

1. Original Network (with baseline durations):

8 5 10 3 6 2 3 4 6 5 5 1 2 3 4 5 6 7 8

2. Baseline Evaluation (showing original ES, LF and Critical Path):

The diagram below represents the original network and its initial forward/backward pass calculation before updating. The original critical path is 1-3-4-5-6-8 with a total duration of 24 days.

8 5 10 3 6 2 3 4 6 5 5 0,0 8,13 10,10 13,13 15,15 19,19 18,19 24,24 1 2 3 4 5 6 7 8

Original Critical Path Duration Calculation:

Toriginal = 10 + 3 + 2 + 4 + 5 = 24  days

3. Updated Network (at Day 12):

The diagram below represents the updated network at the end of 12 days. Completed activities are shown as dashed lines with their actual durations in green. Active activities are shown with their remaining durations in red from the update day (day 12). The new critical path is 1-2-7-8 with an updated project duration of 36 days.

10 0 (act: 5) 0 (act: 8) 0 (act: 3) 9 6 3 4 10 5 5 22,22 12,20 12,20 18,26 22,31 31,31 36,36 12,12 1 2 3 4 5 6 7 8

Updated Project Duration Calculation (from day 12):

Tupdated = 12 + 10 + 9 + 5 = 36  days
Conclusion of Updating Due to the drastic delay in activity 1-2 (which took 12 days to execute up to this point and still needs 10 more days), the critical path has shifted from the bottom path to the top path (1-2-7-8). The project completion date has been delayed from 24 days to 36 days, representing a net slippage of 12 days.