CPM / Project Updating
Updating is a process which involves comparison between actual execution and original plan at regular intervals. If it requires, necessary actions are taken to get things back on schedule. Hence, it requires an upward flow of information.
To perform updating of a network, the following information must be collected:
Updating Template: Below is a typical layout of the data collection table used during updating:
| Activity | Completed? (Y/N) | If Yes: Actual Completion Time | If In Progress: Remaining Duration | If Yet to Start: Estimated Duration |
|---|---|---|---|---|
| — | — | — | — | — |
| — | — | — | — | — |
| — | — | — | — | — |
Updating is done whenever there is a major change in the duration of any activity. The frequency of updating depends heavily on the scale of the project:
Problem Statement: The figure below shows the network diagram of a project, which is to be updated at the end of 12 days. The following conditions exist at the time of updating:
1. Original Network (with baseline durations):
2. Baseline Evaluation (showing original ES, LF and Critical Path):
The diagram below represents the original network and its initial forward/backward pass calculation before updating. The original critical path is 1-3-4-5-6-8 with a total duration of 24 days.
Original Critical Path Duration Calculation:
3. Updated Network (at Day 12):
The diagram below represents the updated network at the end of 12 days. Completed activities are shown as dashed lines with their actual durations in green. Active activities are shown with their remaining durations in red from the update day (day 12). The new critical path is 1-2-7-8 with an updated project duration of 36 days.
Updated Project Duration Calculation (from day 12):