What is an A-O-N Diagram?
In an Activity-on-Node (AON) diagram system, activities are represented by nodes, and their interdependence is established using arrows (→).
Alternative Name: This network diagram is also commonly referred to as a Precedence Diagram.
Node Representation: Nodes are usually represented by rectangles or squares.
Activity Numbering: The method for numbering activities remains identical to the AOA (Activity-on-Arrow) diagram system.
A-O-N Node Structure
Inside an AON node, all key scheduling variables are clearly designated within or adjacent to the node boundaries, making it highly self-sufficient:
EST & LST: The Earliest Start Time () and Latest Start Time () are located on the left side of the incoming arrow.
EFT & LFT: The Earliest Finish Time () and Latest Finish Time () are located on the right side of the outgoing arrow.
Node Layout: The activity's description is housed in the upper box. The bottom-left cell holds the activity duration (time), and the bottom-right cell holds the Activity number.
Important Features of the AON System
AON diagrams possess several key properties that distinguish them from AOA diagrams:
No Event Nodes: Events have no distinct place in AON. Because of this, the AON system is not suitable for PERT (Program Evaluation and Review Technique) networks.
Self-Sufficient Nodes: The diagram contains all essential activity times (, , , ) on the nodes themselves, which allows for better scheduling and monitoring.
Better Rescheduling: The self-contained data layout makes rescheduling and modifying the project timeline much easier.
Elimination of Dummies: One of the biggest advantages of AON is that it completely eliminates the need for dummy activities.
Start and Finish Milestones
To keep the project network structured with single entry and exit points, start and finish milestones are introduced:
Debut Activity (S): When multiple activities start simultaneously, a debut (start) activity is placed at the beginning. Its duration is set to zero.
Finish Activity (F): Similarly, when multiple activities finish together, a finish activity with a duration of zero is placed at the very end.
Comparison: AOA vs. AON
Below is a direct comparison of network logic representation between Activity-on-Arrow (AOA) and Activity-on-Node (AON) diagrams: