CPM / A-O-N Diagram

A-O-N Diagram

Converted from handwritten notes — CPM_8_AON_Diagram, page 1 & 2

Doc No.CPM-08
StatusDraft — Awaiting Review
Converted27-07-2026
Approved—

What is an A-O-N Diagram?

In an Activity-on-Node (AON) diagram system, activities are represented by nodes, and their interdependence is established using arrows (→).

A-O-N Node Structure

Inside an AON node, all key scheduling variables are clearly designated within or adjacent to the node boundaries, making it highly self-sufficient:

EST LST Activity description time Activity number EFT LFT

Important Features of the AON System

AON diagrams possess several key properties that distinguish them from AOA diagrams:

Start and Finish Milestones

To keep the project network structured with single entry and exit points, start and finish milestones are introduced:

Comparison: AOA vs. AON

Below is a direct comparison of network logic representation between Activity-on-Arrow (AOA) and Activity-on-Node (AON) diagrams:

1. Simple Sequential Dependency
AOA 1 A 2 B 3
AON A B
2. Diverging Activities (1 Predecessor, 2 Successors)
AOA 1 A 2 B 3 C 4
AON A B C
3. Dummy Dependency (Eliminated in AON)
AOA 1 A 2 B 3 C: dummy 4 D 5 E 6
AON A B D E
4. Multiple Starts/Finishes (AON Milestones Required)
AOA 1 A 2 B C D 3 E 4
AON S A B C D E F

S (Start Milestone): Debut/start activity introduced to join activities A, C, and D starting simultaneously. (Duration = 0)

F (Finish Milestone): Finish activity introduced to join activities B, C, and E terminating simultaneously. (Duration = 0)