CPM / Project Crashing

Project Crashing & Time-Cost Optimization

Converted from handwritten notes — S:\GATE CE\OCR Tool Test\CPM_5_Crashing, pages 1-15

Doc No.CPM-05
StatusDraft — Awaiting Review
Converted27-07-2026
Approved—

Introduction to Project Crashing

In any project management framework, two critical and interconnected aspects must be considered for execution:

To establish the precise relationship between time and cost, a cost model, time-cost relationship, or project cost function must be developed.

Handwritten page 1 diagram

Your original — page 1

Time → Total project cost → minm cost optimum project duration
Definition The project time corresponding to the minimum total project cost is called the optimum project duration.

Project Cost Components

The total cost of executing any project is categorized into two main components:

Handwritten page 2 cost tree

Your original — page 2 (Top)

Total project cost direct cost indirect cost overheads outage loss

1. Indirect Cost

Indirect costs are those expenses that cannot be directly associated or assigned to any individual activity of the project. Instead, they are associated with a group of activities or the project as a whole. Mathematically:

Indirect Cost = Overhead Charges + Outage Loss
Handwritten page 2 indirect cost curve

Your original — page 2 (Bottom)

Time → indirect cost → overhead expense outage loss

Indirect cost always increases with time. Overhead charges increase linearly with time, while outage loss increases exponentially (non-linearly) with time. Hence, the total indirect cost increases non-linearly over time.

Simplification Note For ease of standard calculations in GATE problems, we assume that indirect cost increases linearly with time by neglecting outage losses.

2. Direct Cost

Direct costs are those expenses that can be directly charged to a specific activity of the project. Examples include the cost of materials, labor, equipment usage, etc.

Direct Cost Behavior & Cost Slope

Direct cost behaves inversely to indirect cost: it decreases as the activity duration increases (since executing slowly is generally cheaper, up to a point). If we crash (expedite) the activity, direct cost increases sharply.

Handwritten page 3 direct cost curve

Your original — page 3

Time → cost → tc → Crash time tn → normal time Cc crash cost Cn normal cost cost slope = Cc−Cn / tn−tc marginal increase in project cost reducing project time crashing potential = tn − tc θ Δy Δx Slope = Δy/Δx

Definition of terms:

For accurate mathematical calculations, a segmented approach to cost slopes is adopted. However, for simplicity, a straight-line approach is widely used. The cost slope represents the increase in direct cost when the duration of an activity is reduced by one unit of time.

Cost Slope = Cc − Cn tn − tc

Total Project Cost Curve

The total project cost is the sum of direct and indirect costs. Because direct cost decreases with time and indirect cost increases with time, the sum creates a U-shaped curve with a distinct minimum point.

Handwritten page 5 total cost curve

Your original — page 5

Time → Total project cost → direct cost Indirect cost Total project cost optimum project duration

Steps for Project Crashing

The process of optimizing project time and cost is carried out systematically as follows:

Solved Example — Network Optimization

Problem Statement: Determine the minimum cost and optimum duration of a project. The duration and cost data for each activity are given in the table below. The indirect cost of the project is ₹ 800/day. Draw the time-scale version of the network.

Activity Normal Time (t_n) Normal Cost (C_n) Crash Time (t_c) Crash Cost (C_c)
A-B2 days₹ 10,0002 days₹ 10,000
A-C7 days₹ 5,0003 days₹ 9,000
B-C6 days₹ 3,0003 days₹ 4,200
B-D5 days₹ 2,0004 days₹ 2,500
C-D0 days (Dummy)₹ 00 days₹ 0
C-E9 days₹ 6,0004 days₹ 9,000
D-F11 days₹ 6,0006 days₹ 10,000
E-F6 days₹ 7,0003 days₹ 9,100

Step-by-Step Crashing Solution

1. Cost Slope Calculation Table

Activity t_n C_n t_c C_c Cost Slope (₹/day)
A-B2₹ 10,0002₹ 10,0000
A-C7₹ 5,0003₹ 9,0001,000
B-C6₹ 3,0003₹ 4,200400
B-D5₹ 2,0004₹ 2,500500
C-D0₹ 00₹ 00
C-E9₹ 6,0004₹ 9,000600
D-F11₹ 6,0006₹ 10,000800
E-F6₹ 7,0003₹ 9,100700

2. Initial Network (Stage 0)

Handwritten page 8 initial network

Your original — page 8

A 0,0 B 2,2 C 8,8 D 8,12 E 17,17 F 23,23 2(2) 7(3) 6(3) 5(4) 0(0) 9(4) 11(6) 6(3)

3. Initial Time Scale Diagram

Handwritten page 9 initial time scale

Your original — page 9

A B C D E F 2(2) 6(3) 9(4) 6(3) 7(3) 1 day float 5(4) 1 day float 0(0) 11(6) 4 days float 0 2 8 17 23

4. Cost Calculations (Initial)

Total Cost (Stage 0) = Direct Cost + Indirect Cost Direct Cost = 10,000 + 5,000 + 3,000 + 2,000 + 6,000 + 6,000 + 7,000 = 39,000  ₹ Indirect Cost = 23 × 800 = 18,400  ₹ Total Cost = 39,000 + 18,400 = 57,400  ₹

1st Stage of Crashing:

Crashing Stage 1 (Reduction to 22 Days)

Although activity B-C has a crashing potential of 3 days, we cannot crash it by the full 3 days immediately because it is restrained by parallel paths. The activities A-C and B-D both have only 1 day of float. Crashing B-C by more than 1 day would not reduce the project duration unless we also crash A-C. Hence, we crash B-C by 1 day.

Handwritten page 10 network

Your original — page 10

1 2 3 A B C D E F 2(2) 5(3) 9(4) 6(3) 7(3) 5(4) 0(0) 11(6) 4 days float 0 2 7 16 22
Total Project Cost (Stage 1) = Direct Cost + Indirect Cost Direct Cost = 39,000 + 400 = 39,400  ₹ Indirect Cost = 22 × 800 = 17,600  ₹ Total Cost = 39,400 + 17,600 = 57,000  ₹

Crashing Stage 2 (Reduction to 18 Days)

With two critical paths now active (A-B-C-E-F & A-C-E-F), further reduction requires crashing activities that reduce both paths simultaneously. We analyze the available options and their combined slopes:

Option 2 (C-E) is the cheapest with a slope of ₹ 600/day. However, we cannot crash it by its full potential of 5 days. The parallel activity D-F has only 4 days of float. Crashing CE by 5 days would leave the project duration at 18 days due to path D-F. Thus, we only crash C-E by 4 days.

Handwritten page 11 network

Your original — page 11

1 2 3 A B C D E F 2(2) 5(3) 5(4) 6(3) 7(3) 5(4) 0(0) 11(6) 0 2 7 12 18
Total Project Cost (Stage 2) = 57,000 − 4 × 800 + 4 × 600 = 56,200  ₹

Crashing Stage 3 (Reduction to 17 Days)

Now all paths are critical. We have 5 distinct critical paths:

To crash the project further, we must crash a combination of activities that reduces all 5 critical paths simultaneously. The available alternatives are:

Alternative 2 (CE + DF) is the cheapest at ₹ 1,400/day. CE has 1 day of crashing potential left (5−4=1 day left). Hence, we crash CE and DF simultaneously by 1 day.

Handwritten page 12 network

Your original — page 12

1 2 A B C D E F 2(2) 5(3) 4(4) 6(3) 7(3) 5(4) 0(0) 10(6) 0 2 7 11 17
Total Project Cost (Stage 3) = 56,200 − 1 × 800 + 1 × 1400 = 56,800  ₹
Economic Observation Note that the combined cost slope (₹ 1,400/day) is greater than the indirect cost rate (₹ 800/day). Hence, although duration is successfully reduced, the total cost increases from ₹ 56,200 to ₹ 56,800. The cost-optimum project duration is therefore 18 days.

Crashing Stage 4 & 5 (Further Reduction to 13 Days)

1. 4th Stage of Crashing (Reduction to 14 Days)

Since CE is now at its crash limit (4 days), we analyze the remaining alternatives to crash both the bottom paths and the top path:

Alternative 2 is the cheapest at ₹ 1,500/day. Activity E-F can crash by up to 3 days (6−3=3 days). We crash EF and DF simultaneously by 3 days.

Handwritten page 13 network

Your original — page 13

1 A B C D E F 2(2) 5(3) 4(4) 3(3) 7(3) 5(4) 0(0) 7(6) 0 2 7 11 14
Total Project Cost (Stage 4) = 56,800 − 3 × 800 + 3 × 1,500 = 58,900  ₹

2. 5th Stage of Crashing (Reduction to 13 Days)

Since both CE and EF are at their crash limits, the only way to reduce the bottom paths further is to crash the initial activities AC and BC. We must also crash BD to reduce the top path. The combined slope is ₹ 1,900/day. We can crash them by 1 day before BD reaches its crash limit of 4 days.

Handwritten page 14 network

Your original — page 14 (Top)

A B C D E F 2(2) 4(3) 4(4) 3(3) 6(3) 4(4) 0(0) 7(6) 0 2 6 10 13
Total Project Cost (Stage 5) = 58,900 − 1 × 800 + 1 × 1,900 = 60,000  ₹

Cost Summary & Optimization Curve

The network has no further crashing potential (as per source notes), and the total project cost for each project duration is compiled and plotted below:

Project Duration (days) Direct Cost (₹) Indirect Cost (₹) Total Cost (₹) Critical Path(s)
23 days (Initial)₹ 39,000₹ 18,400₹ 57,400A-B-C-E-F
22 days₹ 39,400₹ 17,600₹ 57,000A-B-C-E-F, A-C-E-F
18 days (Optimum)₹ 41,800₹ 14,400₹ 56,200A-B-C-E-F, A-C-E-F, A-B-D-F (and paths through C-D-F)
17 days₹ 43,200₹ 13,600₹ 56,800All paths critical
14 days₹ 47,700₹ 11,200₹ 58,900All paths critical
13 days (Crash Limit)₹ 49,600₹ 10,400₹ 60,000All paths critical
Handwritten page 14 cost graph

Your original — page 14 (Bottom)

Time (days) → Total project cost (₹) → 55,000 55,500 56,000 56,500 57,000 57,500 58,000 58,500 59,000 59,500 60,000 5 10 15 20 25 18 days 56,200 ₹
Antigravity Technical Analysis — Discrepancy in Source Notes The handwritten source notes state that the project cannot be crashed further than 13 days. However, this is a minor conceptual error:

At 13 days, the activities on the path A-B-D-F are A-B (duration 2, crash limit 2), B-D (duration 4, crash limit 4), and D-F (duration 7, crash limit 6). Since D-F still has 1 day of crashing potential remaining, it is possible to crash the network by 1 day to 12 days.

To do this, we must crash A-C (slope 1,000), B-C (slope 400), and D-F (slope 800) simultaneously. The combined cost slope would be ₹ 2,200/day, bringing the total project duration to its absolute minimum physical crash limit of 12 days at a cost of ₹ 61,400.

Additional Example — Series Activities

Question: Three activities A, B, and C are in series. Their estimated direct costs in ₹ for various durations in days are shown below. Determine the minimum total cost of the activities for a total duration of 28 days, without considering overhead costs.

Handwritten page 15 series activities

Your original — page 15

1 2 3 4 A B C (10, 2000) (9, 2200) (8, 2500) Δ=200 Δ=300 (8, 2500) (7, 2800) (6, 3100) Δ=300 Δ=300 (12, 800) (11, 900) (10, 1000) Δ=100 Δ=100

Solution Walkthrough

The objective is to reduce the combined duration of series activities A, B, and C to exactly 28 days with the minimum cost increase. We start from their maximum (least-cost) durations:

tA = 10  days, tB = 8  days, tC = 12  days Initial Duration = 10 + 8 + 12 = 30  days Initial Direct Cost = 2,000 + 2,500 + 800 = 5,300  ₹

To reduce the project duration from 30 days to 28 days, we must crash activities by a total of 2 days. We compare the cost slopes (cost increase per day) for the next crashing steps:

Since Activity C has the minimum cost slope (₹ 100/day), we crash C by 2 days. The new duration of C becomes 10 days.

Final Duration = 10 + 8 + 10 = 28  days Minimum Cost = 2,000 + 2,500 + 1,000 = 5,500  ₹