In any project management framework, two critical and interconnected aspects must be considered for execution:
Project Time: Calculated along the critical path of the network.
Total Project Cost: Related directly to project time, though this relationship is non-linear.
To establish the precise relationship between time and cost, a cost model, time-cost relationship, or project cost function must be developed.
Your original — page 1
Definition
The project time corresponding to the minimum total project cost is called the optimum project duration.
Project Cost Components
The total cost of executing any project is categorized into two main components:
Your original — page 2 (Top)
1. Indirect Cost
Indirect costs are those expenses that cannot be directly associated or assigned to any individual activity of the project. Instead, they are associated with a group of activities or the project as a whole. Mathematically:
Overhead Charges: Recurring expenses required to run the project. Examples include establishment charges, expense for maintenance, insurance charges, and services during operation.
Outage Loss: Costs incurred due to project delays or losses in productivity. Examples include loss in profit, liquidated damages, and penalty for delay of completion.
Your original — page 2 (Bottom)
Indirect cost always increases with time. Overhead charges increase linearly with time, while outage loss increases exponentially (non-linearly) with time. Hence, the total indirect cost increases non-linearly over time.
Simplification Note
For ease of standard calculations in GATE problems, we assume that indirect cost increases linearly with time by neglecting outage losses.
2. Direct Cost
Direct costs are those expenses that can be directly charged to a specific activity of the project. Examples include the cost of materials, labor, equipment usage, etc.
Direct Cost Behavior & Cost Slope
Direct cost behaves inversely to indirect cost: it decreases as the activity duration increases (since executing slowly is generally cheaper, up to a point). If we crash (expedite) the activity, direct cost increases sharply.
Your original — page 3
Definition of terms:
Normal Time (): The standard duration that an estimator assigns to an activity under normal working conditions.
Crash Time (): The minimum possible duration in which an activity can be completed by deploying an infinite number of resources.
Normal Cost (): The direct cost associated with executing the activity in its normal time.
Crash Cost (): The direct cost associated with executing the activity in its minimum crash time.
For accurate mathematical calculations, a segmented approach to cost slopes is adopted. However, for simplicity, a straight-line approach is widely used. The cost slope represents the increase in direct cost when the duration of an activity is reduced by one unit of time.
Total Project Cost Curve
The total project cost is the sum of direct and indirect costs. Because direct cost decreases with time and indirect cost increases with time, the sum creates a U-shaped curve with a distinct minimum point.
Your original — page 5
Steps for Project Crashing
The process of optimizing project time and cost is carried out systematically as follows:
Step 1: Draw the initial network diagram and identify the critical path.
Step 2: Highlight the critical path on the network or time-scale diagram.
Step 3: Calculate the cost slope of each activity.
Step 4: Identify the critical activities along the critical path and rank them by cost slope.
Step 5: Begin crashing the critical activity with the minimum cost slope first.
Step 6: Continue crashing this activity until its crashing potential is exhausted, or a parallel path becomes critical.
Step 7: If a new critical path is formed, identify the new critical activities. To crash further, identify the cheapest combination of activities in parallel that reduces all critical paths simultaneously.
Step 8: Calculate the cost implications at each step and plot the final project cost vs. time graph.
Solved Example — Network Optimization
Problem Statement: Determine the minimum cost and optimum duration of a project. The duration and cost data for each activity are given in the table below. The indirect cost of the project is ₹ 800/day. Draw the time-scale version of the network.
Activity
Normal Time (t_n)
Normal Cost (C_n)
Crash Time (t_c)
Crash Cost (C_c)
A-B
2 days
₹ 10,000
2 days
₹ 10,000
A-C
7 days
₹ 5,000
3 days
₹ 9,000
B-C
6 days
₹ 3,000
3 days
₹ 4,200
B-D
5 days
₹ 2,000
4 days
₹ 2,500
C-D
0 days (Dummy)
₹ 0
0 days
₹ 0
C-E
9 days
₹ 6,000
4 days
₹ 9,000
D-F
11 days
₹ 6,000
6 days
₹ 10,000
E-F
6 days
₹ 7,000
3 days
₹ 9,100
Step-by-Step Crashing Solution
1. Cost Slope Calculation Table
Activity
t_n
C_n
t_c
C_c
Cost Slope (₹/day)
A-B
2
₹ 10,000
2
₹ 10,000
0
A-C
7
₹ 5,000
3
₹ 9,000
1,000
B-C
6
₹ 3,000
3
₹ 4,200
400
B-D
5
₹ 2,000
4
₹ 2,500
500
C-D
0
₹ 0
0
₹ 0
0
C-E
9
₹ 6,000
4
₹ 9,000
600
D-F
11
₹ 6,000
6
₹ 10,000
800
E-F
6
₹ 7,000
3
₹ 9,100
700
2. Initial Network (Stage 0)
Your original — page 8
Normal Project Duration: 23 days.
Critical Path (Initial): A-B-C-E-F (Events A → B → C → E → F).
3. Initial Time Scale Diagram
Your original — page 9
4. Cost Calculations (Initial)
1st Stage of Crashing:
The critical path is A-B-C-E-F.
Among the critical activities, activity A-B has a cost slope of 0 but no crashing potential ().
Among the remaining critical activities (B-C, C-E, E-F), B-C has the least cost slope (₹ 400/day) and its crashing potential is 3 days ( days).
Crashing Stage 1 (Reduction to 22 Days)
Although activity B-C has a crashing potential of 3 days, we cannot crash it by the full 3 days immediately because it is restrained by parallel paths. The activities A-C and B-D both have only 1 day of float. Crashing B-C by more than 1 day would not reduce the project duration unless we also crash A-C. Hence, we crash B-C by 1 day.
New Project Duration: 22 days.
New Critical Paths:A-B-C-E-F and A-C-E-F.
Your original — page 10
Crashing Stage 2 (Reduction to 18 Days)
With two critical paths now active (A-B-C-E-F & A-C-E-F), further reduction requires crashing activities that reduce both paths simultaneously. We analyze the available options and their combined slopes:
Option 1 (Crash AC + BC + BD): Cost slope = ₹ 1,000 + 400 + 500 = ₹ 1,900/day. (B-D must be crashed in parallel to prevent the lower path B-D-F from becoming critical and blocking project reduction).
Option 2 (Crash C-E): Cost slope = ₹ 600/day. (CE lies on both critical paths).
Option 3 (Crash E-F): Cost slope = ₹ 700/day. (EF lies on both critical paths).
Option 2 (C-E) is the cheapest with a slope of ₹ 600/day. However, we cannot crash it by its full potential of 5 days. The parallel activity D-F has only 4 days of float. Crashing CE by 5 days would leave the project duration at 18 days due to path D-F. Thus, we only crash C-E by 4 days.
New Project Duration: 18 days.
New Critical Paths: Almost all paths are now critical.
Your original — page 11
Crashing Stage 3 (Reduction to 17 Days)
Now all paths are critical. We have 5 distinct critical paths:
A-B-C-E-F
A-B-C-D-F
A-C-E-F
A-B-D-F
A-C-D-F
To crash the project further, we must crash a combination of activities that reduces all 5 critical paths simultaneously. The available alternatives are:
Alternative 1: AC + BC + BD = 1000 + 400 + 500 = ₹ 1,900/day.
Alternative 2: CE + DF = 600 + 800 = ₹ 1,400/day.
Alternative 3: EF + DF = 700 + 800 = ₹ 1,500/day.
Alternative 2 (CE + DF) is the cheapest at ₹ 1,400/day. CE has 1 day of crashing potential left ( day left). Hence, we crash CE and DF simultaneously by 1 day.
New Project Duration: 17 days.
CE duration becomes 4 days (its crash limit).
DF duration becomes 10 days.
Your original — page 12
Economic Observation
Note that the combined cost slope (₹ 1,400/day) is greater than the indirect cost rate (₹ 800/day). Hence, although duration is successfully reduced, the total cost increases from ₹ 56,200 to ₹ 56,800. The cost-optimum project duration is therefore 18 days.
Crashing Stage 4 & 5 (Further Reduction to 13 Days)
1. 4th Stage of Crashing (Reduction to 14 Days)
Since CE is now at its crash limit (4 days), we analyze the remaining alternatives to crash both the bottom paths and the top path:
Alternative 1: AC + BC + BD = ₹ 1,900/day.
Alternative 2: EF + DF = 700 + 800 = ₹ 1,500/day.
Alternative 2 is the cheapest at ₹ 1,500/day. Activity E-F can crash by up to 3 days ( days). We crash EF and DF simultaneously by 3 days.
New Project Duration: 14 days.
EF duration becomes 3 days (its crash limit).
DF duration becomes 7 days.
Your original — page 13
2. 5th Stage of Crashing (Reduction to 13 Days)
Since both CE and EF are at their crash limits, the only way to reduce the bottom paths further is to crash the initial activities AC and BC. We must also crash BD to reduce the top path. The combined slope is ₹ 1,900/day. We can crash them by 1 day before BD reaches its crash limit of 4 days.
New Project Duration: 13 days.
BD duration becomes 4 days (its crash limit).
BC duration becomes 4 days.
AC duration becomes 6 days.
Your original — page 14 (Top)
Cost Summary & Optimization Curve
The network has no further crashing potential (as per source notes), and the total project cost for each project duration is compiled and plotted below:
Project Duration (days)
Direct Cost (₹)
Indirect Cost (₹)
Total Cost (₹)
Critical Path(s)
23 days (Initial)
₹ 39,000
₹ 18,400
₹ 57,400
A-B-C-E-F
22 days
₹ 39,400
₹ 17,600
₹ 57,000
A-B-C-E-F, A-C-E-F
18 days (Optimum)
₹ 41,800
₹ 14,400
₹ 56,200
A-B-C-E-F, A-C-E-F, A-B-D-F (and paths through C-D-F)
17 days
₹ 43,200
₹ 13,600
₹ 56,800
All paths critical
14 days
₹ 47,700
₹ 11,200
₹ 58,900
All paths critical
13 days (Crash Limit)
₹ 49,600
₹ 10,400
₹ 60,000
All paths critical
Your original — page 14 (Bottom)
Antigravity Technical Analysis — Discrepancy in Source Notes
The handwritten source notes state that the project cannot be crashed further than 13 days. However, this is a minor conceptual error:
At 13 days, the activities on the path A-B-D-F are A-B (duration 2, crash limit 2), B-D (duration 4, crash limit 4), and D-F (duration 7, crash limit 6). Since D-F still has 1 day of crashing potential remaining, it is possible to crash the network by 1 day to 12 days.
To do this, we must crash A-C (slope 1,000), B-C (slope 400), and D-F (slope 800) simultaneously. The combined cost slope would be ₹ 2,200/day, bringing the total project duration to its absolute minimum physical crash limit of 12 days at a cost of ₹ 61,400.
Additional Example — Series Activities
Question: Three activities A, B, and C are in series. Their estimated direct costs in ₹ for various durations in days are shown below. Determine the minimum total cost of the activities for a total duration of 28 days, without considering overhead costs.
Your original — page 15
Solution Walkthrough
The objective is to reduce the combined duration of series activities A, B, and C to exactly 28 days with the minimum cost increase. We start from their maximum (least-cost) durations:
To reduce the project duration from 30 days to 28 days, we must crash activities by a total of 2 days. We compare the cost slopes (cost increase per day) for the next crashing steps:
Activity A: Crashing from 10 to 9 days costs an additional ₹ 200/day.
Activity B: Crashing from 8 to 7 days costs an additional ₹ 300/day.
Activity C: Crashing from 12 to 11 days (and 11 to 10 days) costs an additional ₹ 100/day.
Since Activity C has the minimum cost slope (₹ 100/day), we crash C by 2 days. The new duration of C becomes 10 days.