Introduction to CPM
The Critical Path Method (CPM) is a project management technique developed independently from PERT, focusing on project scheduling and optimization.
Development: Developed independently of PERT, CPM is quite similar to it. Mr. Walker and J.E. Kelly of Remington Rand were involved in developing CPM for chemical plants in the U.S.A.
Application: CPM is mostly used in construction projects where there is sufficient/detailed information about the activities. It is used for optimization (trending) between project cost and project completion time.
Distribution: In PERT, activities follow a Beta distribution with three time estimates. In CPM, activities follow a normal distribution with a narrow range of variance, thus requiring only a single time estimate.
Difference between PERT and CPM
Feature / Property
PERT
CPM
Orientation
Event oriented (focuses on milestones)
Activity oriented (focuses on tasks)
Approach & Use
Follows probabilistic approach; used for R&D (Research & Development) projects
Follows deterministic approach; used for construction projects
Time Estimates
Three time estimates given for completion of an activity
Only a single time estimate is given to an activity
Probability Distribution
Activity follows a Beta distribution
Activity follows a Normal distribution
Cost-Time Relation
Project cost is directly proportional to time. Hence, to minimize cost, time must be reduced.
Cost model has to be developed to determine minimum project cost.
Criticality Concept
Critical activities/events are identified with the concept of Slack.
Critical activities are determined with the concept of Float.
Time Notation
Activity time is denoted by or
Activity time is denoted by or
Time Estimates in CPM
1. Event Times
Event times are calculated during network passes to determine earliest and latest event times.
Earliest Event Occurrence Time ():
Calculated during the forward pass:
Latest Allowable Occurrence Time ():
Calculated during the backward pass:
2. Activity Times
Activity times describe the schedule boundaries for individual activities, computed from the event times of their start (tail) and end (head) nodes.
Activity times and event relationships
Earliest Start Time (EST): The earliest time by which an activity can commence.
Earliest Finish Time (EFT): The earliest time by which an activity can complete.
Latest Start Time (LST): The latest time by which an activity can commence without delaying the project completion time.
Latest Finish Time (LFT): The latest time by which an activity can be completed without delaying the project.
Activity Floats
Float is the extra available time by which an activity can be delayed without affecting the overall project completion time.
1. Total Float ()
Total float is the maximum available time by which an activity can be delayed without affecting the project completion time.
2. Free Float ()
Free float is the time by which an activity can be delayed without affecting the earliest start time of the succeeding activity.
Network sequence for Free Float analysis
Slack of Head Event ()
. Hence, Free Float represents Total Float minus the slack of the succeeding (head) event.
3. Independent Float ()
Independent float is the minimum available time by which an activity can be delayed such that all preceding activities are finished as late as possible and succeeding activities start as early as possible.
Slack of Tail Event ()
. Independent Float represents Free Float minus the slack of the preceding (tail) event.
4. Interfering Float ()
Interfering float is the float that is equal to the head event slack.
Important Rules & Behaviors
Non-negativity: Free float and independent float can never be negative. If a negative mathematical value is calculated, it is taken as zero.
Interdependency: The float of any activity affects the floats of its preceding and succeeding activities.
Free Float Limit: Free float affects the float of the preceding activity, whereas it does not affect the float of the succeeding activity.
Independent Isolation: Independent float does not affect the float of either preceding or succeeding activities.
Float Relationship Bar Chart
Logical alignment of CPM activity floats
Super-critical and Sub-critical Activities
Activities in a network are classified according to their total float, which directly impacts the project scheduling flexibility.
Critical Activity: Total float is exactly zero. These tasks have no scheduling flexibility; any delay directly delays the project.
Sub-critical Activity: Total float is positive (). These activities have spare time and can be delayed within their float limit.
Super-critical Activity: Total float is negative (). This occurs when a target completion date is fixed that is shorter than the calculated duration.
Critical Path
The critical path is the longest path in terms of time through the network. It is the sequence of critical activities from start to end.
Mandatory Condition
In CPM network analysis, the critical path is formed by joining the activities having zero total float.
Solved Example
Question: A building project consists of 12 activities having normal duration required to perform various activities and relationship among activities as given below.
Activity
Predecessor Activity
Normal Duration (days)
A
—
7
B
—
5
C
A
10
D
A
5
E
B
8
F
B
6
G
C
5
H
C
4
I
D
10
J
E
5
K
F
8
L
G, H, I, J
9
Solution: Draw the network diagram, calculate activity times, different floats and identify the critical path.
1. Network Diagram (Activity-on-Arrow)
2. Calculations Table
Activity
Duration ()
EST
EFT
LST
LFT
FT
FF
FID
FIN
A
7
0
7
0
7
0
0
0
0
B
5
0
5
4
9
4
0
0
4
C
10
7
17
7
17
0
0
0
0
D
5
7
12
7
12
0
0
0
0
E
8
5
13
9
17
4
0
0
4
F
6
5
11
17
23
12
0
0
12
G
5
17
22
17
22
0
0
0
0
H
4
17
21
18
22
1
0
0
1
I
10
12
22
12
22
0
0
0
0
J
5
13
18
17
22
4
4
0
0
K
8
11
19
23
31
12
12
0
0
L
9
22
31
22
31
0
0
0
0
Critical Path Determination
The network contains two critical paths (highlighted in red, having zero total float for all activities):
A → D → I → L (Nodes 1→2→5→9→10) with project duration of 31 days.
A → C → G → L (Nodes 1→2→4→9→10) with project duration of 31 days.