CPM / Critical Path Method

Critical Path Method (CPM)

Converted from handwritten notes — CPM 4 CPM.pdf, page 1-9

Doc No.CPM-04
StatusDraft — Awaiting Review
Converted27-07-2026
Approved—

Introduction to CPM

The Critical Path Method (CPM) is a project management technique developed independently from PERT, focusing on project scheduling and optimization.

Difference between PERT and CPM

Feature / Property PERT CPM
Orientation Event oriented (focuses on milestones) Activity oriented (focuses on tasks)
Approach & Use Follows probabilistic approach; used for R&D (Research & Development) projects Follows deterministic approach; used for construction projects
Time Estimates Three time estimates given for completion of an activity Only a single time estimate is given to an activity
Probability Distribution Activity follows a Beta distribution Activity follows a Normal distribution
Cost-Time Relation Project cost is directly proportional to time. Hence, to minimize cost, time must be reduced. Cost model has to be developed to determine minimum project cost.
Criticality Concept Critical activities/events are identified with the concept of Slack. Critical activities are determined with the concept of Float.
Time Notation Activity time is denoted by teij or te Activity time is denoted by tij or t

Time Estimates in CPM

1. Event Times

Event times are calculated during network passes to determine earliest and latest event times.

2. Activity Times

Activity times describe the schedule boundaries for individual activities, computed from the event times of their start (tail) and end (head) nodes.

i TEi, TLi j TEj, TLj tij
Activity times and event relationships

Activity Floats

Float is the extra available time by which an activity can be delayed without affecting the overall project completion time.

1. Total Float (FT)

Total float is the maximum available time by which an activity can be delayed without affecting the project completion time.

FT = ( TLj − TEi ) − tij FT = LST − EST = LFT − EFT

2. Free Float (FF)

Free float is the time by which an activity can be delayed without affecting the earliest start time of the succeeding activity.

i j TEj k tij TEi
Network sequence for Free Float analysis
FF = ( TEj − TEi ) − tij FF = FT − ( TLj − TEj ) = FT − Sj
Slack of Head Event (Sj) Sj=TLj−TEj. Hence, Free Float represents Total Float minus the slack of the succeeding (head) event.

3. Independent Float (FID)

Independent float is the minimum available time by which an activity can be delayed such that all preceding activities are finished as late as possible and succeeding activities start as early as possible.

FID = ( TEj − TLi ) − tij FID = FF − ( TLi − TEi ) = FF − Si
Slack of Tail Event (Si) Si=TLi−TEi. Independent Float represents Free Float minus the slack of the preceding (tail) event.

4. Interfering Float (FIN)

Interfering float is the float that is equal to the head event slack.

FIN = Sj = FT − FF

Important Rules & Behaviors

Float Relationship Bar Chart

EST = TEi LFT = TLj TLi TEj Si tij (Duration) EFT = TEi + tij FT = LFT - EFT FT = LST - EST tij LST = TLj - tij FF = FT - Sj Sj = FIN FID = FF - Si Si
Logical alignment of CPM activity floats

Super-critical and Sub-critical Activities

Activities in a network are classified according to their total float, which directly impacts the project scheduling flexibility.

Types of Total Float FT > 0 Sub-critical Activity FT = 0 Critical Activity FT < 0 Super-critical Activity

Critical Path

The critical path is the longest path in terms of time through the network. It is the sequence of critical activities from start to end.

Mandatory Condition In CPM network analysis, the critical path is formed by joining the activities having zero total float.

Solved Example

Question: A building project consists of 12 activities having normal duration required to perform various activities and relationship among activities as given below.

Activity Predecessor Activity Normal Duration (days)
A—7
B—5
CA10
DA5
EB8
FB6
GC5
HC4
ID10
JE5
KF8
LG, H, I, J9

Solution: Draw the network diagram, calculate activity times, different floats and identify the critical path.

1. Network Diagram (Activity-on-Arrow)

1 0,0 2 7,7 3 5,9 4 17,17 5 12,12 6 13,17 7 11,23 8 21,22 9 22,22 10 31,31 A7 B5 C10 D5 E8 F6 H4 G5 I10 J5 K8 Dummy0 L9

2. Calculations Table

Activity Duration (t) EST EFT LST LFT FT FF FID FIN
A707070000
B505494004
C107177170000
D57127120000
E85139174004
F65111723120012
G5172217220000
H4172118221001
I10122212220000
J5131817224400
K811192331121200
L9223122310000
Critical Path Determination The network contains two critical paths (highlighted in red, having zero total float for all activities):
  1. A → D → I → L (Nodes 1→2→5→9→10) with project duration of 31 days.
  2. A → C → G → L (Nodes 1→2→4→9→10) with project duration of 31 days.