CPM / Project Evaluation and Review Technique (PERT)

Project Evaluation and Review Technique (PERT)

Converted from handwritten notes — CPM-03, pages 1-20

Doc No.CPM-03
StatusDraft — Awaiting Review
Converted27-07-2026
Approved—

Review copy — each redrawn diagram below is shown next to your original handwritten page. Remove all "Your original" panels before publishing.

Introduction to PERT

The Project Evaluation and Review Technique (PERT) is an event-oriented probabilistic project management method designed for planning, scheduling, and monitoring complex, non-repetitive projects.

Event-Oriented Nature Because the duration of activities is highly uncertain and subject to many external variables, the focus shifts to milestone events (start and finish of major tasks) rather than trackable continuous activities.

Time Estimation Approaches

Activity durations can be approached in two primary ways depending on project characteristics:

  1. Deterministic Approach:
    • The planner provides a single, highly accurate time estimate.
    • Used when the project is repetitive or when substantial past experience is available.
  2. Probabilistic Approach:
    • The planner provides a time range within which the duration is expected to fall, reflecting high uncertainty.
    • Used in unique, R&D, or non-repetitive projects where exact durations cannot be predicted.

Three Time Estimates

To incorporate uncertainty into durations, PERT requires three separate time estimates for each activity:

  1. Optimistic Time (to):
    • The minimum possible time required to complete the activity if everything goes exceptionally well, under ideal conditions.
  2. Pessimistic Time (tp):
    • The maximum possible time required to complete the activity if everything goes wrong and abnormal conditions prevail.
    • Note: Delays due to catastrophic events (e.g., floods, earthquakes, fires, pandemics, labor strikes) are not included in this estimate.
  3. Most Likely Time (tm):
    • The duration that would occur most frequently if the activity were repeated many times. It represents the time required under normal conditions.

By definition, these estimates satisfy the mathematical inequality:

to<tm<tp
Uncertainty Mapping Even though these three estimates are simple to make, they capture key mathematical bounds that allow us to construct a full probability density function for the activity duration.

Frequency Distribution Curves

A Frequency Distribution Curve represents the relationship between the number of jobs completed (frequency) and the amount of time taken. It models how durations vary upon repetition.

Handwritten source, page 3 frequency distribution

Your original — page 3

time No. of jobs to tm tp

Symmetrical Frequency Distribution Curve

Skewed Distributions

When a frequency distribution is not symmetrical, it has skewness. This represents skew in the probability of completing a job:

Handwritten source, right skewed Handwritten source, left skewed

Your original — page 3 bottom

Mode Median Mean Right skewed (Positive Skewness) Mode < Median < Mean Mean Median Mode Left skewed (Negative Skewness) Mean < Median < Mode

Right Skewed vs. Left Skewed Frequency Curves

Probability Distribution Curves

In project scheduling, a Probability Distribution Curve is preferred over a frequency distribution curve. The height is standardized such that the total area under the curve is exactly equal to unity (Area=1), allowing the calculation of cumulative probability up to any time t.

Probability of occurrence till time t = Shaded Area Total Area = Shaded Area 1 = Shaded Area
Handwritten source, page 4 probability distribution

Your original — page 4

0.0 0.1 0.2 0.3 0.4 f(x) −3σ −2σ −1σ 0 1σ 2σ 3σ 0.1% 2.1% 13.6% 34.1% 34.1% 13.6% 2.1% 0.1% time (t)

Standard Normal Probability Distribution Areas (Standardized Area = 1)

Aesthetics & Terminology of Skewness

Depending on the relation of the three time estimates, the probability distribution curves take distinct forms representing different scheduling philosophies:

Symmetry Type Curve Classification (As per Notes) Mathematical Distribution Approach / Significance
Positive Skew Left skewed (peak on left) BETA Distribution Optimistic Approach: Most likely time is closer to optimistic time.
Symmetrical Symmetrical Distribution Normal / Gaussian Distribution Normal Approach: Most likely time is midway between optimistic and pessimistic times.
Negative Skew Right skewed (peak on right) BETA Distribution Pessimistic Approach: Most likely time is closer to pessimistic time.
Standard Statistics Clarification In standard probability textbooks, a distribution with its peak on the left and tail on the right is named right-skewed (since it has a positive skewness coefficient). The handwritten notes refer to this as "Left skewed" because the bulk of the data/peak lies to the left. We have retained the student's local naming conventions while drawing mathematically accurate shapes in the SVGs.
Handwritten source, page 5 top

Your original — page 5 top

Median Mode Positive Skew OPTIMISTIC APPROACH Mean/Med/Mode Symmetrical (Normal) NORMAL APPROACH Median Mode Negative Skew PESSIMISTIC APPROACH

Visual Comparison of Skew Types and Project Scheduling Approaches

Normal Distribution Area Percentages

The probability of completing a project or activity within a specified standard deviation boundary (±zσ) is constant for all normal curves. These standard thresholds are:

Standard Deviation Range Cumulative Area Under Curve (Probability %)
±1σ 68.27% (approximated as 68.2%)
±2σ 95.45% (approximated as 95.4%)
±3σ 99.73% (approximated as 99.8% in some textbooks)
Handwritten source, page 5 bottom

Your original — page 5 bottom

0 1σ 2σ 3σ −1σ −2σ −3σ 68.2% 95.4% 99.8%

Normal Curve Standard Deviation Bound Percentages

Standard Deviation & Variance Formulas

If we assume that the optimistic and pessimistic durations (to and tp) cover 99.8% of the total possible area under the normal curve (representing the ±3σ limits), the full range is equal to six standard deviations:

tp − to = 6 σ

This yields the core formulas for standard deviation (σ) and variance (V) of a single PERT activity:

σ = tp−to 6
V = σ2 = ( tp−to 6 ) 2
Key Property of Uncertainty Note that standard deviation (σ) and variance (V) are completely independent of the most likely time (tm). They only measure the spread (or range) between the extreme bounds. A larger variance indicates higher project uncertainty.

Expected Activity Time (te)

Under the Beta distribution, the expected (mean) duration of an activity is calculated by a weighted average that places 4 times the weight on the most likely time:

te = to + 4 tm + tp 6
Handwritten source, page 7 beta distribution

Your original — page 7

x PDF te → not optimistic nor pessimistic (50% probability line)

Overlapping Beta Distributions with Varying Skewness

Beta Function Definition

The mathematically rigorous probability density function of the Beta distribution is defined in terms of the Gamma function (Γ):

f (x,α,β) = xα−1 ⋅ (1−x)β−1 ∫01 xα−1 ⋅ (1−x)β−1 dx = xα−1 ⋅ (1−x)β−1 B(α,β)  where  B(α,β) = Γ(α)⋅Γ(β) Γ(α+β)

Central Limit Theorem in Networks

According to the Central Limit Theorem, if a network path consists of a fairly large number of serial, independent activities (n), the probability distribution of the total path duration will approximate a Normal Distribution, regardless of the individual activities following Beta distributions.

For a serial path consisting of activities 1→2→3→4:

Handwritten source, page 8 path

Your original — page 8

1 te1-2 2 te2-3 3 te3-4 4

Activities in series along a path

  1. Expected Path Duration (tepath):
    te1−4 = te1−2 + te2−3 + te3−4
  2. Standard Deviation of Path (σpath):
    σ1−4 = σ1−22 + σ2−32 + σ3−42

Event Times: Forward Pass

The earliest time an event can occur is calculated during the Forward Pass, working from the start node to the end node. An event is achieved if and only if all activities leading into it have finished.

TEj = max ( TEi + teij )
Handwritten network Handwritten TE formula

Your original — page 9 network & formula

1 TE=0 TL=0 2 TE=2 TL=2 3 TE=5 TL=5 4 TE=9 TL=9 5 TE=13 TL=13 2 3 5 4 4

AOA Network Diagram with Earliest expected event occurrence times (TE)

Note: TE for the initial event of any network diagram is always taken as zero.

Event Times: Backward Pass & Slack

The latest allowable occurrence time (TL) for an event is calculated during the Backward Pass, working from the end node back to the start node. It represents the latest time an event can occur without extending the overall project completion date.

TLi = min ( TLj − teij )

Slack (s)

Slack is a property of an event that represents the amount of time the event's occurrence can be delayed without affecting the scheduled project completion time.

s = TL − TE
Handwritten TL formula Handwritten slack network

Your original — page 10 network & formula

1 TE,TL=(0,0) 2 (4,6) Slack s=2 3 (5,5) Slack s=0 4 (11,11) 4 5 9 5 6

Network Diagram showing (TE, TL) event times and Slack calculation

Types of Slack

Event slack can be positive, zero, or negative, defining the schedule status of the milestone:

  1. Positive Slack (s>0, TL>TE):
    • Indicates the event is ahead of schedule.
    • More than enough resources are deployed.
    • These events are called sub-critical events.
  2. Zero Slack (s=0, TL=TE):
    • Indicates the event is exactly on schedule.
    • Resources deployed are just enough.
    • These events are called critical events.
  3. Negative Slack (s<0, TL<TE):
    • Indicates the event is behind schedule.
    • Resources deployed are insufficient.
    • These events are called super-critical events.

Critical Path

In any network diagram, there are a large number of paths connecting the initial and final events. The path that takes the longest amount of time is called the Critical Path. It governs the overall duration of the project.

Zero Slack Condition While it is mandatory that slack along the critical path is zero (or at its minimum value), having zero slack at a node is a necessary but not sufficient condition for that node/activity to be on the critical path.

Multiple Critical Paths

If a project network has multiple parallel critical paths (each having the same maximum duration):

Probability of Project Completion

Using the Central Limit Theorem, the probability of completing a project within a scheduled duration (Ts) can be determined using a standard normal curve centered at the expected project completion time (TE):

P = Area (ACD) Area (ACDB)
Handwritten normal distribution

Your original — page 14

TE Ts C D A B Normal distribution

Normal Curve Area representing Completion Probability

Normal Deviate / Probability Factor (z)

The distance between the scheduled time (Ts) and the expected time (TE) in terms of standard deviation is the standard normal deviate (z):

z = Ts − TE σcritical path
Handwritten Z types

Your original — page 15 bottom

Types of Probability factor (z) z < 0 P < 50% z = 0 P = 50% z > 0 P > 50%

Classification of Probability Factor (z) and Completion Probability (P)

Solved Question 1

Problem Statement

A father notes that his teenage daughter uses the telephone. She takes not less than 5 minutes for a call and sometimes as much as an hour. 15 minutes calls are more frequent than calls of any other duration. If the daughter's calls were an activity in a PERT project, determine:

  1. Expected phone call duration (te)
  2. Variance (V)
  3. In scheduling the project, how much time will you allocate to this activity?

Solution

From the statement, we can map the three PERT time estimates (converting hours to minutes):

1. Expected Phone Call Duration (te)

te = to + 4 tm + tp 6 = 5+4(15)+60 6 = 1256 = 20 56 min

Converting the fractional part to seconds: 56×60=50 seconds.

Expected Duration = 20 minutes 50 seconds

2. Variance (V)

V = σ2 = ( tp−to 6 ) 2 = ( 60−56 ) 2 = ( 556 ) 2 = 302536 ≈ 84.03 min2
Source Code Correction Note In the handwritten notes (page 16), the variance formula was transcribed as σ2=tp−to6 due to a quick writing slip, but the calculation itself correctly squared the term as (556)2=84.3 min2 (or accurately 84.03). We have corrected the formula notation in our typesetting for students.

3. Scheduled Time Allocation

In project scheduling, the time allocated to an activity is its expected completion time (te).

Allocated Time = 20 minutes 50 seconds

Solved Question 2

Problem Statement

A project is expected to take 15 months along the critical path having a standard deviation of 3 months. What is the probability of completing the project within:

  1. 15 months
  2. 21 months
  3. 12 months

Solution

Given expected critical path duration (TE=15 months) and path standard deviation (σ=3 months). We apply standard normal conversion:

1. Scheduled time Ts=15 months

z = 15−15 3 = 0 ⇒ P = 50 %

2. Scheduled time Ts=21 months

z = 21−15 3 = 2

For z=2, the half-area is 47.7% (from mean to 2σ). Thus:

P = 50 % + 47.7 % = 97.7 %

3. Scheduled time Ts=12 months

z = 12−15 3 = − 1

For z=−1, the half-area is 34.1% (from mean to 1σ). Since scheduled time is below the expected mean:

P = 50 % − 34.1 % = 15.9 %
Handwritten normal distribution Q2

Your original — page 17

0 1σ 2σ −1σ 34.1% 34.1% 13.6% σ = 34.1% 2σ = 47.7% 3σ = 49.8%

Symmetrical Area mapping values for half-normal ranges

Solved Question 3

Problem Statement

Construct the network diagram for the following activities of a PERT project, whose relationships and time estimates are given below. Determine:

  1. The probability of completing the job in 32 days.
  2. The project completion duration for a probability of 50%.
Activity Predecessor to tm tp
P—369
QP, T489
RQ459
S—333
TS81417
U—147
WS2514
YS4713
ZU, W61530

Standard Z values provided: P(z=−1.5)=0.07, P(z=−1.3)=0.10, P(z=−1.0)=0.16.

Solution

First, we calculate the expected duration (te) and variance (σ2) for each activity using:

te = to+4tm+tp 6  and  σ2 = ( tp−to 6 ) 2
Activity Predecessors to tm tp te (days) Variance σ2
P—3696.01.0
QP, T4897.50.694
RQ4595.50.694
S—3333.00.0
TS8141713.52.25
U—1474.01.0
WS25146.04.0
YS47137.52.25
ZU, W6153016.016.0

Network Diagram & Critical Path

Using the precedence relationships, we construct the AOA network diagram and perform the forward and backward passes:

Handwritten network Q3

Your original — page 19

1 (0,0) 2 (3,3) 3 (16.5,16.5) 4 (9,13.5) 5 (24,24) 6 (29.5,29.5) P = 6 S = 3 U = 4 T = 13.5 W = 6 Y = 7.5 Q = 7.5 R = 5.5 Z = 16

Project network diagram. Activities S–T–Q–R form the critical path (highlighted in red).

Critical path is: S → T → Q → R (or path events 1-2-3-5-6)

Standard Deviation of the Critical Path

σcritical path = σS2 + σT2 + σQ2 + σR2 = (3−36)2 + (17−86)2 + (9−46)2 + (9−46)2 = 0 + 2.25 + 0.694 + 0.694 = 3.638 ≈ 1.907 days

Probability of Completion in 32 Days

Find z at scheduled duration Ts=32 days:

z = 32−29.5 1.907 = 1.31

Using the symmetry of the normal distribution and the provided Z values:

We perform linear interpolation to find P(z=+1.31) between 1.30 and 1.50:

P ( z = 1.31 ) = 0.9 + 0.93−0.90 1.5−1.3 × (1.31−1.3) = 0.9 + 0.030.2 × 0.01 = 0.9 + 0.15 × 0.01 = 0.9015 ⇒ 90.15 %

Probability of project completion in 32 days = 90.15%