CPM / Project Evaluation and Review Technique (PERT)
Project Evaluation and Review Technique (PERT)
Converted from handwritten notes — CPM-03, pages 1-20
Doc No.CPM-03
StatusDraft — Awaiting Review
Converted27-07-2026
Approved—
Review copy — each redrawn diagram below is shown next to your original handwritten page. Remove all "Your original" panels before publishing.
Introduction to PERT
The Project Evaluation and Review Technique (PERT) is an event-oriented probabilistic project management method designed for planning, scheduling, and monitoring complex, non-repetitive projects.
Applications: PERT is predominantly used in research and development (R&D) types of projects, manufacturing industries, space programs, drug development, and defense systems.
History: Developed by the US Navy in cooperation with Lockheed Aircraft Corporation for the planning and control of the Polaris fleet ballistic missile program.
Nature of Durations: Since there is no historical database or certainty regarding activity durations in unique projects, PERT is intrinsically event-oriented rather than activity-oriented.
Event-Oriented Nature
Because the duration of activities is highly uncertain and subject to many external variables, the focus shifts to milestone events (start and finish of major tasks) rather than trackable continuous activities.
Time Estimation Approaches
Activity durations can be approached in two primary ways depending on project characteristics:
Deterministic Approach:
The planner provides a single, highly accurate time estimate.
Used when the project is repetitive or when substantial past experience is available.
Probabilistic Approach:
The planner provides a time range within which the duration is expected to fall, reflecting high uncertainty.
Used in unique, R&D, or non-repetitive projects where exact durations cannot be predicted.
Three Time Estimates
To incorporate uncertainty into durations, PERT requires three separate time estimates for each activity:
Optimistic Time ():
The minimum possible time required to complete the activity if everything goes exceptionally well, under ideal conditions.
Pessimistic Time ():
The maximum possible time required to complete the activity if everything goes wrong and abnormal conditions prevail.
Note: Delays due to catastrophic events (e.g., floods, earthquakes, fires, pandemics, labor strikes) are not included in this estimate.
Most Likely Time ():
The duration that would occur most frequently if the activity were repeated many times. It represents the time required under normal conditions.
By definition, these estimates satisfy the mathematical inequality:
Uncertainty Mapping
Even though these three estimates are simple to make, they capture key mathematical bounds that allow us to construct a full probability density function for the activity duration.
Frequency Distribution Curves
A Frequency Distribution Curve represents the relationship between the number of jobs completed (frequency) and the amount of time taken. It models how durations vary upon repetition.
Normal Distribution: A symmetrical, unimodal curve where the most likely value lies precisely at the center, dividing the curve symmetrically.
Skewed Distributions: Frequency curves can also be skewed left or right, indicating that the activity is more likely to take longer or shorter than the midpoint value.
Your original — page 3
Symmetrical Frequency Distribution Curve
Skewed Distributions
When a frequency distribution is not symmetrical, it has skewness. This represents skew in the probability of completing a job:
Your original — page 3 bottom
Right Skewed vs. Left Skewed Frequency Curves
Probability Distribution Curves
In project scheduling, a Probability Distribution Curve is preferred over a frequency distribution curve. The height is standardized such that the total area under the curve is exactly equal to unity (), allowing the calculation of cumulative probability up to any time .
Your original — page 4
Standard Normal Probability Distribution Areas (Standardized Area = 1)
Aesthetics & Terminology of Skewness
Depending on the relation of the three time estimates, the probability distribution curves take distinct forms representing different scheduling philosophies:
Symmetry Type
Curve Classification (As per Notes)
Mathematical Distribution
Approach / Significance
Positive Skew
Left skewed (peak on left)
BETA Distribution
Optimistic Approach: Most likely time is closer to optimistic time.
Symmetrical
Symmetrical Distribution
Normal / Gaussian Distribution
Normal Approach: Most likely time is midway between optimistic and pessimistic times.
Negative Skew
Right skewed (peak on right)
BETA Distribution
Pessimistic Approach: Most likely time is closer to pessimistic time.
Standard Statistics Clarification
In standard probability textbooks, a distribution with its peak on the left and tail on the right is named right-skewed (since it has a positive skewness coefficient). The handwritten notes refer to this as "Left skewed" because the bulk of the data/peak lies to the left. We have retained the student's local naming conventions while drawing mathematically accurate shapes in the SVGs.
Your original — page 5 top
Visual Comparison of Skew Types and Project Scheduling Approaches
Normal Distribution Area Percentages
The probability of completing a project or activity within a specified standard deviation boundary () is constant for all normal curves. These standard thresholds are:
Standard Deviation Range
Cumulative Area Under Curve (Probability %)
68.27% (approximated as 68.2%)
95.45% (approximated as 95.4%)
99.73% (approximated as 99.8% in some textbooks)
Your original — page 5 bottom
Normal Curve Standard Deviation Bound Percentages
Standard Deviation & Variance Formulas
If we assume that the optimistic and pessimistic durations ( and ) cover 99.8% of the total possible area under the normal curve (representing the limits), the full range is equal to six standard deviations:
This yields the core formulas for standard deviation () and variance () of a single PERT activity:
Key Property of Uncertainty
Note that standard deviation () and variance () are completely independent of the most likely time (). They only measure the spread (or range) between the extreme bounds. A larger variance indicates higher project uncertainty.
Expected Activity Time ()
Under the Beta distribution, the expected (mean) duration of an activity is calculated by a weighted average that places 4 times the weight on the most likely time:
Probability threshold: The expected time represents the point on the distribution curve where there is exactly a 50% chance of the activity being completed earlier, and a 50% chance of taking longer.
Geometric meaning: A vertical line drawn through divides the area under the Beta distribution curve into two equal halves.
Difference from Mode: represents the mean (average value) of the distribution, whereas represents the mode (highest peak of the distribution).
Your original — page 7
Overlapping Beta Distributions with Varying Skewness
Beta Function Definition
The mathematically rigorous probability density function of the Beta distribution is defined in terms of the Gamma function ():
Central Limit Theorem in Networks
According to the Central Limit Theorem, if a network path consists of a fairly large number of serial, independent activities (), the probability distribution of the total path duration will approximate a Normal Distribution, regardless of the individual activities following Beta distributions.
For a serial path consisting of activities :
Your original — page 8
Activities in series along a path
Expected Path Duration ():
Standard Deviation of Path ():
Event Times: Forward Pass
The earliest time an event can occur is calculated during the Forward Pass, working from the start node to the end node. An event is achieved if and only if all activities leading into it have finished.
Your original — page 9 network & formula
AOA Network Diagram with Earliest expected event occurrence times (TE)
Note: TE for the initial event of any network diagram is always taken as zero.
Event Times: Backward Pass & Slack
The latest allowable occurrence time () for an event is calculated during the Backward Pass, working from the end node back to the start node. It represents the latest time an event can occur without extending the overall project completion date.
Slack ()
Slack is a property of an event that represents the amount of time the event's occurrence can be delayed without affecting the scheduled project completion time.
Your original — page 10 network & formula
Network Diagram showing (TE, TL) event times and Slack calculation
Types of Slack
Event slack can be positive, zero, or negative, defining the schedule status of the milestone:
Positive Slack (, ):
Indicates the event is ahead of schedule.
More than enough resources are deployed.
These events are called sub-critical events.
Zero Slack (, ):
Indicates the event is exactly on schedule.
Resources deployed are just enough.
These events are called critical events.
Negative Slack (, ):
Indicates the event is behind schedule.
Resources deployed are insufficient.
These events are called super-critical events.
Critical Path
In any network diagram, there are a large number of paths connecting the initial and final events. The path that takes the longest amount of time is called the Critical Path. It governs the overall duration of the project.
Longest Path Time-wise: Since all paths must be completed before the project is considered finished, the longest path determines the minimum duration in which the project can be completed.
Sensitivity: Any delay along the critical path will directly extend the project duration. To reduce the project duration, we must reduce the durations of activities along the critical path.
Critical Events & Activities: Events along the critical path are critical events (zero slack), and activities along it are critical activities.
Zero Slack Condition
While it is mandatory that slack along the critical path is zero (or at its minimum value), having zero slack at a node is a necessary but not sufficient condition for that node/activity to be on the critical path.
Multiple Critical Paths
If a project network has multiple parallel critical paths (each having the same maximum duration):
In PERT analysis, the most critical path is defined as the one having the larger standard deviation () or larger variance ().
This is because a path with a larger standard deviation is associated with a wider distribution range and higher risk of delay.
Probability of Project Completion
Using the Central Limit Theorem, the probability of completing a project within a scheduled duration () can be determined using a standard normal curve centered at the expected project completion time ():
Your original — page 14
Normal Curve Area representing Completion Probability
Normal Deviate / Probability Factor ()
The distance between the scheduled time () and the expected time () in terms of standard deviation is the standard normal deviate ():
Your original — page 15 bottom
Classification of Probability Factor (z) and Completion Probability (P)
Solved Question 1
Problem Statement
A father notes that his teenage daughter uses the telephone. She takes not less than 5 minutes for a call and sometimes as much as an hour. 15 minutes calls are more frequent than calls of any other duration. If the daughter's calls were an activity in a PERT project, determine:
Expected phone call duration ()
Variance ()
In scheduling the project, how much time will you allocate to this activity?
Solution
From the statement, we can map the three PERT time estimates (converting hours to minutes):
Optimistic Time:
Most Likely Time:
Pessimistic Time:
1. Expected Phone Call Duration ()
Converting the fractional part to seconds: .
Expected Duration = 20 minutes 50 seconds
2. Variance ()
Source Code Correction Note
In the handwritten notes (page 16), the variance formula was transcribed as due to a quick writing slip, but the calculation itself correctly squared the term as (or accurately 84.03). We have corrected the formula notation in our typesetting for students.
3. Scheduled Time Allocation
In project scheduling, the time allocated to an activity is its expected completion time ().
Allocated Time = 20 minutes 50 seconds
Solved Question 2
Problem Statement
A project is expected to take 15 months along the critical path having a standard deviation of 3 months. What is the probability of completing the project within:
15 months
21 months
12 months
Solution
Given expected critical path duration () and path standard deviation (). We apply standard normal conversion:
1. Scheduled time
2. Scheduled time
For , the half-area is 47.7% (from mean to 2σ). Thus:
3. Scheduled time
For , the half-area is 34.1% (from mean to 1σ). Since scheduled time is below the expected mean:
Your original — page 17
Symmetrical Area mapping values for half-normal ranges
Solved Question 3
Problem Statement
Construct the network diagram for the following activities of a PERT project, whose relationships and time estimates are given below. Determine:
The probability of completing the job in 32 days.
The project completion duration for a probability of 50%.
Activity
Predecessor
to
tm
tp
P
—
3
6
9
Q
P, T
4
8
9
R
Q
4
5
9
S
—
3
3
3
T
S
8
14
17
U
—
1
4
7
W
S
2
5
14
Y
S
4
7
13
Z
U, W
6
15
30
Standard Z values provided: , , .
Solution
First, we calculate the expected duration () and variance () for each activity using:
Activity
Predecessors
to
tm
tp
te (days)
Variance σ2
P
—
3
6
9
6.0
1.0
Q
P, T
4
8
9
7.5
0.694
R
Q
4
5
9
5.5
0.694
S
—
3
3
3
3.0
0.0
T
S
8
14
17
13.5
2.25
U
—
1
4
7
4.0
1.0
W
S
2
5
14
6.0
4.0
Y
S
4
7
13
7.5
2.25
Z
U, W
6
15
30
16.0
16.0
Network Diagram & Critical Path
Using the precedence relationships, we construct the AOA network diagram and perform the forward and backward passes:
Your original — page 19
Project network diagram. Activities S–T–Q–R form the critical path (highlighted in red).
Critical path is: S → T → Q → R (or path events 1-2-3-5-6)
Project completion time: .
50% probability project duration: At , standard normal deviate . Thus scheduled time is exactly the expected duration.
Completion duration for 50% probability = 29.5 days
Standard Deviation of the Critical Path
Probability of Completion in 32 Days
Find at scheduled duration :
Using the symmetry of the normal distribution and the provided Z values:
Given
Given
We perform linear interpolation to find between 1.30 and 1.50:
Probability of project completion in 32 days = 90.15%