CPM / Fundamental of Network
Review copy — each redrawn diagram below is shown next to your original handwritten page. Remove all "Your original" panels before publishing.
A network diagram is a flow diagram that represents the sequential logical relationships between the various activities and events of a project.
An Activity is a specific task or job within a project that consumes resources (such as labor, materials, machinery) and time.
Your original — page 1
AOA Activity Representation (Tail event i to Head event j)
Activities are classified by their relationship to other tasks in the network structure:
Activities that must be performed sequentially, one after another, are series activities.
Your original — page 1
Series activities: performed one after another (A → B → C)
Activities that can be performed simultaneously and are independent of each other are parallel or concurrent activities.
Your original — page 2
Parallel / Concurrent activities: performed simultaneously and independently
A Dummy Activity is an artificial activity introduced into the network diagram that does not consume any time or resources.
Your original — page 2
Dummy activity 2-3 establishing dependency of D on both A and B
Dummies serve two primary purposes in network diagrams: grammatical representation and logical representation.
A dummy is used to prevent drawing two parallel arrows between the same two events. In network logic, each activity must be uniquely identified by its start (tail) and end (head) events.
Your original — page 3
Grammatical dummy resolving parallel dependency between i and k
A dummy is used to maintain correct logical relationships and avoid a single activity having a dual identity in the project flow. The activity's unique execution path is preserved.
Your original — page 3
Logical dummy resolving dual identity of activity P
As shown in the comparison above, drawing two different arrows for activity P in fig(a) violates network rules because one activity cannot have dual identity. The correct logic is shown in fig(b) where a single activity P is ended at a node, and dummies branch to both dependent paths.
An Event is a specific instance of time that signifies the beginning or completion of one or more activities. It represents the achievement of a project milestone.
Commonly used shapes for events include circular, rectangular, oval, and square nodes:
Your original — page 4
Typical event node shapes
Events are categorized based on their position relative to the activities:
An event that signifies the beginning of one or more activities. If a particular tail event represents the absolute start of the project, it is called the Initial Event.
Your original — page 4
Tail Event (Event 1): Activity begins from here
An event that signifies the completion of one or more activities. If a particular head event represents the absolute completion of the project, it is called the End / Final Event.
Your original — page 4
Head Event (Event 2): Activity terminates here
An event that acts as a head event for one or more activities, and simultaneously acts as a tail event for one or more succeeding activities.
Your original — page 5
Dual Role Event: Acts as both a head and a tail event
To keep the network diagram clean and to minimize redundancy, specific logical rules apply to dummy activity usage:
If a dummy is the only activity coming out from a node, then it can be eliminated by merging its tail and head events.
Your original — page 5
If a dummy is the only activity entering into a node, then it can be eliminated by merging its tail and head events.
Your original — page 6
By grouping events with identical predecessor logic, we can significantly reduce the number of dummy activities and nodes:
If multiple activities (e.g. B and D) share the exact same set of immediate predecessors (A and C), they can share a common starting node, eliminating duplicate dummy lines.
Your original — page 6
If multiple activities (e.g. Q and S) depend on the exact same set of predecessors (A and B), we can merge A and B into a single node, reducing the dummy count.
Your original — page 7
If a path already establishes a logical sequence (e.g. A → B → D), a separate parallel dummy representing the same dependency (A → D) is redundant and must be deleted.
Your original — page 7
Dummy activity A1 is redundant and can be safely deleted
Here, activity E starts from Node 4, which depends on D (completing at 3) and dummy A1 (from 2). Because Node 3 can only be reached after A and B are completed, dependency on A is already logically established at Node 4 via path 1 → A → 2 → B → 3 → D → 4. Thus, dummy A1 is redundant.
A standard network diagram must strictly adhere to the following ten rules to be mathematically and logically sound:
Fulkerson's rule provides a systematic method for numbering events in a network diagram. The fundamental rule is: the number of any succeeding event must be strictly greater than its preceding event ( for activity ).
Your original — page 9
Network numbered systematically using Fulkerson's Rule
In large projects where extensive modifications or additions are frequently required, event numbering in simple sequences (1, 2, 3...) can force massive renumbering effort. To avoid this, we use Skip Numbering (numbering in multiples of 10, 100, etc.).
If a new event needs to be added post-commencement, it can be assigned a number in between the terminal node values (e.g. event 35 between 30 and 40) without altering the rest of the network numbering.
Your original — page 9
Skip numbering method: New event 35 inserted between 30 and 60
Network construction commonly suffers from three major logical errors which must be audited and eliminated:
A cyclic error occurs when a path of activities loops back to an earlier event, creating an endless loop where a succeeding activity is a predecessor to its own predecessor.
Your original — page 10
Looping / Cyclic error (invalid endless dependency loop)
A dangling error occurs when an activity is left disconnected in the middle of a project (neither starting from the initial node nor terminating at the final node). A project must have exactly one terminal event.
Your original — page 10
Dangling error: two terminal nodes with no single final event
A wagon wheel error occurs when a single hub node receives a large number of incoming activities and releases a large number of outgoing activities, creating a false logical link where every successor is made dependent on every predecessor.
Your original — page 10
Wagon wheel error: central logic hub making D, E, F dependent on all A, B, C
Wagon wheel errors are extremely difficult to spot because the network looks grammatically correct. However, analyzing dependencies will often show that one activity (e.g. D) only depends on A, not B and C, which requires separating the hub with dummies.
Below are the solved and tabulated exercises for constructing and optimizing network diagrams:
A project consists of 10 activities. Draw an arrow-diagram (AOA) representation of the project.
| Job / Activity | Immediate Predecessors |
|---|---|
| A | — |
| B | A |
| C | A |
| D | A |
| E | B |
| F | C |
| G | D |
| H | D |
| I | E, F, G |
| J | H, I |
Draw the network of a project having seven activities. Activities A, B and C run concurrently. Predecessor relationships are as follows:
| Activity | Immediate Predecessors |
|---|---|
| D | A |
| E | B |
| F | C |
Activity G is the last operation of the project and is also the immediate successor to D, E, and F.
Draw a network diagram for the project having 9 activities, with the following inter-relationships:
The maintenance project of a building consists of ten jobs. The predecessor relationships are identified by their node numbers, as indicated below:
| Job | Identification | Job | Identification |
|---|---|---|---|
| A | (1, 2) | F | (4, 5) |
| B | (2, 3) | G | (4, 7) |
| C | (2, 4) | H | (5, 8) |
| D | (3, 6) | I | (6, 8) |
| E | (3, 5) | J | (7, 8) |
A project plan consisting of ten events has the predecessor relationships as under:
| Event | Immediate Predecessors | Event | Immediate Predecessors |
|---|---|---|---|
| 1 | — | 6 | 3, 5 |
| 2 | 1 | 7 | 3, 4 |
| 3 | 1 | 8 | 3, 7 |
| 4 | 1 | 9 | 7 |
| 5 | 2, 3 | 10 | 3, 6, 8, 9 |
A project consists of 16 activities having their predecessor relationship as follows:
Draw a network diagram with the following activities:
| Job Identification | Immediate Predecessors |
|---|---|
| a | — |
| b | — |
| c | — |
| d | a |
| e | c |
| f | a, b, c |
Draw a network diagram with the following data:
| Job Identification | Immediate Predecessors |
|---|---|
| a | — |
| b | — |
| c | — |
| d | a |
| e | c |
| f | a, b, c, d |
| g | a, b, c, e |
| h | a, b, c |
A project consists of six activities (jobs) designated from A to F, with the following relationships:
A project consists of eight activities M, N, O, P, Q, R, S and T. Draw the network and number the events if:
Draw the network for the following situation:
Draw the network for the following case:
| Rule No. | Relationship Description |
|---|---|
| (i) | A and D start at origin |
| (ii) | C follows A but precedes G |
| (iii) | B follows A but precedes F |
| (iv) | H follows D but precedes L |
| (v) | E follows B and C |
| (vi) | K follows G and H |
| (vii) | J follows F but precedes K |
| (viii) | K, L and E are terminal activities. |
| (ix) | F is independent of C |
| (x) | L is independent of J |
Draw an arrow diagram showing the following relationships:
| Activity | Immediate Predecessor(s) |
|---|---|
| A | — |
| B | — |
| C | — |
| D | A, B |
| E | B, C |
| F | A, B |
| G | C |
| H | D, E, F |
| I | D |
| J | G |
| K | G |
| L | H, J |
| M | K |
| N | I, L |
A project has fourteen activities A through N. The relationships which obtain amongst these activities are given below:
A work project consists of 12 activities, labeled A to L. The sequence of activities is given below:
A project manager developed a network for a project involving 20 jobs labeled from A to T. The list of predecessors is as follows:
| Job | Immediate Predecessors | Job | Immediate Predecessors |
|---|---|---|---|
| A | — | K | G |
| B | — | L | F, G, K |
| C | — | M | H, I |
| D | A, B | N | H, I, J, L |
| E | A, B, C | O | J, L |
| F | A, B, C | P | M, N |
| G | C | Q | O, P |
| H | D, E | R | O |
| I | D, E, F | S | Q, R |
| J | F, G | T | S |
Task: Determine which predecessors shown in the table are redundant. Draw the network using as few dummy jobs as possible.
Draw the network and number the events:
Draw the network for the following data:
Draw the network representing the following activity relationship using minimum number of dummies:
Draw a PERT Network for the following project:
In a construction project, events have been identified as A, B, C, D, E, F, G, H, J, K, L and M.
A part of the network is drawn as follows:
Original Network Segment with Dependency Error
Question: Tabulate the dependencies as shown. If actually Z depends on B & Y and R depends on Y & Q only, is there any error? If yes, correct the error and redraw the corrected network.
Corrected Network Diagram: Isolated Y-completion resolving spurious dependency of R on B