CPM / Fundamental of Network

Fundamental of Network

Converted from handwritten notes — CPM 2 Fundamental of Network.pdf, pages 1-14

Doc No.CPM-02
StatusDraft — Awaiting Review
Converted27-07-2026
Approved—

Review copy — each redrawn diagram below is shown next to your original handwritten page. Remove all "Your original" panels before publishing.

Introduction to Networks

A network diagram is a flow diagram that represents the sequential logical relationships between the various activities and events of a project.

Types of Networks

Note on Terminology Some textbooks or practitioners further classify AOA networks into "PERT" and "CPM" networks. However, in rigorous project management, PERT and CPM are planning and management techniques rather than distinct network types themselves. Both techniques can utilize network diagrams.

Basic Definitions: Activity

An Activity is a specific task or job within a project that consumes resources (such as labor, materials, machinery) and time.

Handwritten source, page 1 activity

Your original — page 1

i j description duration Start of activity End of activity

AOA Activity Representation (Tail event i to Head event j)

Types of Activities

Activities are classified by their relationship to other tasks in the network structure:

1. Series Activities

Activities that must be performed sequentially, one after another, are series activities.

Handwritten source, page 1 series activity

Your original — page 1

A B C

Series activities: performed one after another (A → B → C)

2. Parallel / Concurrent Activities

Activities that can be performed simultaneously and are independent of each other are parallel or concurrent activities.

Handwritten source, page 2 parallel activity

Your original — page 2

A B

Parallel / Concurrent activities: performed simultaneously and independently

3. Dummy Activities

A Dummy Activity is an artificial activity introduced into the network diagram that does not consume any time or resources.

Handwritten source, page 2 dummy activity

Your original — page 2

1 A 2 B 3 C D 4 dummy 2-3

Dummy activity 2-3 establishing dependency of D on both A and B

Use of Dummy Activities

Dummies serve two primary purposes in network diagrams: grammatical representation and logical representation.

1. Grammatical Representation

A dummy is used to prevent drawing two parallel arrows between the same two events. In network logic, each activity must be uniquely identified by its start (tail) and end (head) events.

Handwritten source, page 3 grammatical ambiguity

Your original — page 3

i k Ambiguous representation i j k DUMMY Correct representation

Grammatical dummy resolving parallel dependency between i and k

2. Logical Purpose

A dummy is used to maintain correct logical relationships and avoid a single activity having a dual identity in the project flow. The activity's unique execution path is preserved.

Handwritten source, page 3 logical purpose

Your original — page 3

O P Q P R S fig(a) Incorrect (P has dual identity) O P Q S R fig(b) Correct (resolved via dummy)

Logical dummy resolving dual identity of activity P

As shown in the comparison above, drawing two different arrows for activity P in fig(a) violates network rules because one activity cannot have dual identity. The correct logic is shown in fig(b) where a single activity P is ended at a node, and dummies branch to both dependent paths.

Basic Definitions: Event

An Event is a specific instance of time that signifies the beginning or completion of one or more activities. It represents the achievement of a project milestone.

Event Node Shapes

Commonly used shapes for events include circular, rectangular, oval, and square nodes:

Handwritten source, page 4 event shapes

Your original — page 4

Circular Rectangular Oval Square

Typical event node shapes

Types of Events

Events are categorized based on their position relative to the activities:

1. Tail Event

An event that signifies the beginning of one or more activities. If a particular tail event represents the absolute start of the project, it is called the Initial Event.

Handwritten source, page 4 tail event

Your original — page 4

Tail Event (Event 1): Activity begins from here

2. Head Event

An event that signifies the completion of one or more activities. If a particular head event represents the absolute completion of the project, it is called the End / Final Event.

Handwritten source, page 4 head event

Your original — page 4

Head Event (Event 2): Activity terminates here

3. Dual Role Event

An event that acts as a head event for one or more activities, and simultaneously acts as a tail event for one or more succeeding activities.

Handwritten source, page 5 dual role event

Your original — page 5

Dual Role Event: Acts as both a head and a tail event

Rules for Providing Dummy Activities

To keep the network diagram clean and to minimize redundancy, specific logical rules apply to dummy activity usage:

Rule 1: Dummy leaving a node with no other activities

If a dummy is the only activity coming out from a node, then it can be eliminated by merging its tail and head events.

Handwritten source, page 5 rule 1 dummy

Your original — page 5

Rule 1: Dummy Elimination
Before (Redundant) 1 P 3 2 A R B 4 C
After (Simplified) 3 P 2 A R B 4 C

Rule 2: Dummy entering a node with no other activities

If a dummy is the only activity entering into a node, then it can be eliminated by merging its tail and head events.

Handwritten source, page 6 rule 2 dummy

Your original — page 6

Rule 2: Dummy Elimination
Before (Redundant) 1 A 4 P C 2 B 3 Q D
After (Simplified) 1 A 4 P C B 3 Q D

Dummy Minimization

By grouping events with identical predecessor logic, we can significantly reduce the number of dummy activities and nodes:

1. Minimizing Dummies through Node Sharing

If multiple activities (e.g. B and D) share the exact same set of immediate predecessors (A and C), they can share a common starting node, eliminating duplicate dummy lines.

Handwritten source, page 6 dummy minimization

Your original — page 6

Dummy Minimization (Common Successors)
Before (6 Dummies) 1 A 2 C 3 P Q 4 B 5 D 6 R S
After (4 Dummies) 1 A 2 C 3 P Q 5 B D 6 R S

2. Minimizing Dummies through Predecessor Merging

If multiple activities (e.g. Q and S) depend on the exact same set of predecessors (A and B), we can merge A and B into a single node, reducing the dummy count.

Handwritten source, page 7 dummy minimization 2

Your original — page 7

Dummy Minimization (Common Predecessors)
Before (4 Dummies) 1 A 2 B 3 P Q 4 R S
After (2 Dummies) 1 A B 3 P Q 4 R S

3. Redundant Dummies

If a path already establishes a logical sequence (e.g. A → B → D), a separate parallel dummy representing the same dependency (A → D) is redundant and must be deleted.

Handwritten source, page 7 redundant dummy

Your original — page 7

1 A 2 B 3 C 5 F 6 D 4 E A1 (Redundant)

Dummy activity A1 is redundant and can be safely deleted

Here, activity E starts from Node 4, which depends on D (completing at 3) and dummy A1 (from 2). Because Node 3 can only be reached after A and B are completed, dependency on A is already logically established at Node 4 via path 1 → A → 2 → B → 3 → D → 4. Thus, dummy A1 is redundant.

Rules of Network Construction

A standard network diagram must strictly adhere to the following ten rules to be mathematically and logically sound:

  1. There should be a single initial node (start event) and a single final node (completion event) for the entire project.
  2. An activity can occur if and only if all the preceding activities are completed.
  3. An event can occur if and only if all the preceding activities terminating at that event are finished.
  4. The number of activities should be exactly equal to the number of arrows in the diagram.
  5. The representation of the network should be such that every activity is completed in order to reach the end objective (no dangling paths).
  6. All constraints and interdependencies should be properly shown with the minimum appropriate number of dummies.
  7. The mathematical logic of the network must be maintained.
  8. Time flow in the diagram must proceed from left to right.
  9. Curved arrows should be avoided.
  10. Crossing of two arrows is not allowed. If crossing is completely unavoidable, bridging (forming a small jump curve over the crossed line) should be done.

Fulkerson's Rule for Event Numbering

Fulkerson's rule provides a systematic method for numbering events in a network diagram. The fundamental rule is: the number of any succeeding event must be strictly greater than its preceding event (j>i for activity Aij).

Handwritten source, page 9 Fulkerson's rule

Your original — page 9

1 A 2 B 3 C 4 D 5 E F 6 G H 7

Network numbered systematically using Fulkerson's Rule

Skip Numbering Method

In large projects where extensive modifications or additions are frequently required, event numbering in simple sequences (1, 2, 3...) can force massive renumbering effort. To avoid this, we use Skip Numbering (numbering in multiples of 10, 100, etc.).

If a new event needs to be added post-commencement, it can be assigned a number in between the terminal node values (e.g. event 35 between 30 and 40) without altering the rest of the network numbering.

Handwritten source, page 9 skip numbering

Your original — page 9

10 20 30 40 50 60 70 35

Skip numbering method: New event 35 inserted between 30 and 60

Common Logical Errors in Networks

Network construction commonly suffers from three major logical errors which must be audited and eliminated:

1. Cyclic / Looping Error

A cyclic error occurs when a path of activities loops back to an earlier event, creating an endless loop where a succeeding activity is a predecessor to its own predecessor.

Handwritten source, page 10 cyclic error

Your original — page 10

Looping / Cyclic error (invalid endless dependency loop)

2. Dangling Error

A dangling error occurs when an activity is left disconnected in the middle of a project (neither starting from the initial node nor terminating at the final node). A project must have exactly one terminal event.

Handwritten source, page 10 dangling error

Your original — page 10

Dangling error: two terminal nodes with no single final event

3. Wagon Wheel Error

A wagon wheel error occurs when a single hub node receives a large number of incoming activities and releases a large number of outgoing activities, creating a false logical link where every successor is made dependent on every predecessor.

Handwritten source, page 10 wagon wheel error

Your original — page 10

A B C D E F

Wagon wheel error: central logic hub making D, E, F dependent on all A, B, C

Wagon wheel errors are extremely difficult to spot because the network looks grammatically correct. However, analyzing dependencies will often show that one activity (e.g. D) only depends on A, not B and C, which requires separating the hub with dummies.

Practice Problems

Below are the solved and tabulated exercises for constructing and optimizing network diagrams:

Problem 1

A project consists of 10 activities. Draw an arrow-diagram (AOA) representation of the project.

Job / Activity Immediate Predecessors
A—
BA
CA
DA
EB
FC
GD
HD
IE, F, G
JH, I
Network Logic Solution - Start with Node 1 → A → Node 2. - From Node 2, three activities branch: B (to Node 3), C (to Node 4), and D (to Node 5). - E follows B (Node 3 → E → Node 6). - F follows C (Node 4 → F → Node 6). - G follows D (Node 5 → G → Node 6). - H follows D (Node 5 → H → Node 7). - E, F, and G all terminate at Node 6 to precede activity I (Node 6 → I → Node 8). - J follows H and I (Node 7 and Node 8 must connect, e.g. via dummy 7-8, and then Node 8 → J → Node 9).

Problem 2

Draw the network of a project having seven activities. Activities A, B and C run concurrently. Predecessor relationships are as follows:

Activity Immediate Predecessors
DA
EB
FC

Activity G is the last operation of the project and is also the immediate successor to D, E, and F.

Network Logic Solution - A, B, and C start from the initial Node 1 concurrently. - A → Node 2 → D → Node 5 - B → Node 3 → E → Node 5 - C → Node 4 → F → Node 5 - All D, E, and F terminate at Node 5. - Node 5 → G → Node 6 (G is the final activity).

Problem 3

Draw a network diagram for the project having 9 activities, with the following inter-relationships:

Predecessor Analysis Table - A, B start at origin (Node 1). - D follows A (Node 1 → A → Node 2 → D → Node 3). - C follows B and D. Thus, we run dummy 2-3? No, C depends on B and D. B ends at Node 4, D ends at Node 3. We run a dummy from 4 to 3 (or vice versa) so Node 3 represents completion of B and D. Node 3 → C → Node 5. - F follows C (Node 5 → F → Node 6). - H follows C (Node 5 → H → Node 8). - G follows F (Node 6 → G → Node 7). - E follows A (Node 2 → E → Node 7? No, E precedes I). - I follows G and E. Thus G (ends at 7) and E (ends at 7) terminate at Node 7 → I → Node 8. - H and I terminate at the final Node 8.

Problem 4

The maintenance project of a building consists of ten jobs. The predecessor relationships are identified by their node numbers, as indicated below:

Job Identification Job Identification
A(1, 2)F(4, 5)
B(2, 3)G(4, 7)
C(2, 4)H(5, 8)
D(3, 6)I(6, 8)
E(3, 5)J(7, 8)
Network Logic Solution This is a node-identified activity list. We simply draw the nodes 1 through 8 and connect them with arrows corresponding to each job: - 1 → 2 (A) - 2 → 3 (B), 2 → 4 (C) - 3 → 6 (D), 3 → 5 (E) - 4 → 5 (F), 4 → 7 (G) - 5 → 8 (H) - 6 → 8 (I) - 7 → 8 (J) - Node 8 is the final node.

Problem 5

A project plan consisting of ten events has the predecessor relationships as under:

Event Immediate Predecessors Event Immediate Predecessors
1—63, 5
2173, 4
3183, 7
4197
52, 3103, 6, 8, 9
Network Logic Solution This defines dependencies of events (milestones). We can draw the network using event nodes: - Event 1 is the starting event. - Events 2, 3, 4 occur after 1. - Event 5 occurs after 2 and 3. - Event 6 occurs after 3 and 5. - Event 7 occurs after 3 and 4. - Event 8 occurs after 3 and 7. - Event 9 occurs after 7. - Event 10 occurs after 3, 6, 8, and 9.

Problem 6

A project consists of 16 activities having their predecessor relationship as follows:

Problem 7

Draw a network diagram with the following activities:

Job Identification Immediate Predecessors
a—
b—
c—
da
ec
fa, b, c

Problem 8

Draw a network diagram with the following data:

Job Identification Immediate Predecessors
a—
b—
c—
da
ec
fa, b, c, d
ga, b, c, e
ha, b, c

Problem 9

A project consists of six activities (jobs) designated from A to F, with the following relationships:

  1. A is the first job to be performed.
  2. B and C can be done concurrently, and must follow A.
  3. B must precede D.
  4. E must succeed C, but it cannot start until B is complete.
  5. The last operation F is dependent on the completion of both D and E.
Network Logic Analysis - Node 1 → A → Node 2. - From Node 2, B (to Node 3) and C (to Node 4) emerge. - D follows B (Node 3 → D → Node 5). - E follows C and B. Since B ends at 3 and C ends at 4, we run a dummy from Node 3 to Node 4. E starts from Node 4 (Node 4 → E → Node 5). - F follows D and E. Both D and E terminate at Node 5. Node 5 → F → Node 6.

Problem 10

A project consists of eight activities M, N, O, P, Q, R, S and T. Draw the network and number the events if:

  1. Activities M, N and Q can start concurrently.
  2. Activities O and P are concurrent, and depend on the completion of both M and N.
  3. Activities R and S are concurrent and depend on the completion of O.
  4. Activity T depends upon the completion P, Q and R.
  5. The project is complete when S and T are done.

Problem 11

Draw the network for the following situation:

  1. A is prerequisite on D (A → D).
  2. B is prerequisite on D and E.
  3. C is prerequisite on E (C → E).
  4. D is prerequisite on F (D → F).
  5. E is prerequisite on F (E → F).

Problem 12

Draw the network for the following case:

Rule No. Relationship Description
(i)A and D start at origin
(ii)C follows A but precedes G
(iii)B follows A but precedes F
(iv)H follows D but precedes L
(v)E follows B and C
(vi)K follows G and H
(vii)J follows F but precedes K
(viii)K, L and E are terminal activities.
(ix)F is independent of C
(x)L is independent of J

Problem 13

Draw an arrow diagram showing the following relationships:

Activity Immediate Predecessor(s)
A—
B—
C—
DA, B
EB, C
FA, B
GC
HD, E, F
ID
JG
KG
LH, J
MK
NI, L

Problem 14

A project has fourteen activities A through N. The relationships which obtain amongst these activities are given below:

  1. A is the first operation.
  2. B and C can be performed in parallel and are immediate successor to A.
  3. D, E and F follow B.
  4. G follows E.
  5. H follows D, but it cannot start until E is complete.
  6. I and J succeed G.
  7. F and J precede K.
  8. H and I precede L.
  9. M succeeds L and K.
  10. The last operation N succeeds M and C.

Problem 15

A work project consists of 12 activities, labeled A to L. The sequence of activities is given below:

Problem Description Job A comes first and precedes B, C and D. Both B and C must be done before E starts, and C and D must precede F, but G and H can start as soon as D is completed. Job I succeeds D, E, F, and G; and jobs J and K can start when G, H, and I are all completed. Job L comes after J and K.

Problem 16

A project manager developed a network for a project involving 20 jobs labeled from A to T. The list of predecessors is as follows:

Job Immediate Predecessors Job Immediate Predecessors
A—KG
B—LF, G, K
C—MH, I
DA, BNH, I, J, L
EA, B, COJ, L
FA, B, CPM, N
GCQO, P
HD, ERO
ID, E, FSQ, R
JF, GTS

Task: Determine which predecessors shown in the table are redundant. Draw the network using as few dummy jobs as possible.

Redundancy Analysis - For E (A, B, C): Since D depends on A, B, we can analyze transitively. - For F (A, B, C): Same as E. - For H (D, E): Since E depends on C and A, B, and D depends on A, B. Thus D is a subset of E. We must check if D is redundant. - For I (D, E, F): F depends on A, B, C. E depends on A, B, C. D depends on A, B. So D is redundant for I because E and F already require A, B.

Problem 17

Draw the network and number the events:

  1. Activities A, B and E can start concurrently.
  2. Activities C and D are concurrent and depend on the completion of both A and B.
  3. Activities F and G are concurrent and depend on the completion of C.
  4. Activity H depends on completion of D, E and F.
  5. The project is complete when G and H are done.

Problem 18

Draw the network for the following data:

  1. A and B can be carried out at the same time.
  2. D follows C.
  3. F depends on E and D.
  4. Neither I nor K can be started before B is completed but they can be concurrently performed.
  5. C and E follow A and can be performed concurrently.
  6. E must be carried out before G.
  7. J depends on the completion of I and K.
  8. H can be started when J, F and G are completed.
  9. H is the last activity.

Problem 19

Draw the network representing the following activity relationship using minimum number of dummies:

  1. A, B and C are initial activities.
  2. Q, M and R are finishing activities.
  3. H precedes N but follows D.
  4. E follows D but precedes N.
  5. F and L follow K and B.
  6. F precedes M.
  7. Q follows P, L and N.
  8. L precedes R but follows C.
  9. G follows D.
  10. K and D follow A.
  11. F precedes P but follows G.

Problem 20

Draw a PERT Network for the following project:

  1. A is the first or starting event and K is the end event.
  2. J is a successor event to F.
  3. C and D are successor events to B and B is a successor event to A.
  4. D is a preceding event to G.
  5. E and F occur after event C.
  6. E precedes F.
  7. C restrains the occurrence of G and G precedes H.
  8. H precedes J.
  9. F restrains the occurrence of H.
  10. K succeeds event J.

Problem 21

In a construction project, events have been identified as A, B, C, D, E, F, G, H, J, K, L and M.

Problem 22

A part of the network is drawn as follows:

A (10) B (5) C (6) X (4) Y (10) Z (5) P (7) Q (11) R (12) D1 D2

Original Network Segment with Dependency Error

Question: Tabulate the dependencies as shown. If actually Z depends on B & Y and R depends on Y & Q only, is there any error? If yes, correct the error and redraw the corrected network.

Solution: Yes, there is an error in the drawn network diagram.

Analysis: 1. In the original diagram, dummy D1 connects Node 3 (after B) to Node 7 (after Y), meaning the start of Z depends on Y and B. This is correct. 2. However, dummy D2 connects Node 7 to Node 11 (after Q), meaning the start of R depends on Q and Y. But because Node 7 already receives dummy D1, the logic at Node 7 represents the completion of both B and Y. 3. As a result, dummy D2 carries the dependency of both B and Y to R. Thus, in the drawn network, R is made dependent on Q, Y, and B. This is a spurious dependency error since R should depend only on Y & Q.

Corrected Logic: We must isolate the completion of Y so that it can branch independently to Z (with B) and to R (with Q) without letting B leak into R.

Corrected Network Diagram

A (10) B (5) 8 C (6) X (4) Y (10) 7 Z (5) P (7) Q (11) 11 R (12) D1 D2

Corrected Network Diagram: Isolated Y-completion resolving spurious dependency of R on B