Converted from handwritten notes — CPM 1 Project Management.pdf, pages 1 to 11
Doc No.CPM-01
StatusDraft — Awaiting Review
Converted27-07-2026
Approved—
What is a Project?
A project is a temporary endeavour undertaken to provide a unique product or service.
A project involves a series of activities and tasks that consume resources to achieve some specific goals.
Objectives of a Project
Every project is managed with three primary constraints and objectives in mind:
Project should be completed in a minimum amount of time.
Project should use local resources and manpower.
Project should finish on time with minimum cost.
Elements of Project Management
Planning is the most important technique of project management.
Planning Defined: Planning means defining the objectives of a project and identifying the different tasks and resources required for the timely completion of the project.
Project Breakdown Structures: In the planning phase, the plan is structured using a Work Breakdown Structure (WBS) and an Organizational Breakdown Structure (OBS).
WBS & OBS Function: WBS and OBS identify the set of activities needed to achieve the project goal, as well as the responsibilities of the project team along with the subparts of the project.
In Simple Words
Work Breakdown Structure (WBS) breaks the project's physical deliverables down into smaller, manageable work packages. Organizational Breakdown Structure (OBS) maps these packages to the actual project departments or team members responsible for executing them. WBS defines what needs to be done, and OBS defines who is going to do it.
Scheduling
Scheduling is the process of establishing the sequence of activities and allocating resources (manpower, money, machine, material, space, and time) to each activity.
Scheduling determines the resource requirements at different stages of the project.
The 4M's of Scheduling
Every project schedule must allocate and manage four key resource categories:
Manpower: Labour and personnel requirements.
Money: Financial budget and cash flow.
Machine: Equipment and machinery.
Material: Raw materials and supplies.
Controlling
Controlling is the process of monitoring project progress, identifying deviations from the plan, and taking timely corrective measures.
During controlling, actual project performance is regularly measured against the baseline schedule.
Planning & Scheduling vs. Controlling
There is a clear temporal distinction between planning/scheduling and controlling in project management:
Core Difference
Planning and scheduling are performed before the execution of the project, whereas controlling is performed after the project has started.
Controlling relies on three key management skills:
Directing: The function of the project leader to issue instructions to subordinates, supervise their work, and respond to progress reports.
Co-ordinating: The process of facilitating interaction and collaboration between different project departments.
Organizing: The integration and mobilization of resources required to complete the project.
Methods of Project Management
There are four primary methods used to plan and manage projects:
Bar Chart / Gantt Chart
Milestone Chart
Linked Bar Chart
Network Diagram
Bar Chart (Gantt Chart)
Introduced by Henry Gantt around the 1880s, a bar chart is a graphical representation of activities plotted against time.
Y-Axis: Represents the activities.
X-Axis: Represents time (days, weeks, etc.).
Bar Beginning: Represents the start of an activity.
Bar End: Represents the completion of an activity.
Bar Length: Represents the duration of the activity.
Your original — page 4
Standard Gantt chart representing activities as horizontal bars plotted against time.
Advantages of Bar Charts
Simplicity: Easy to draw and simple to understand without specialized training.
Resource Estimation: Useful for determining resource requirements at any specific stage of the project.
Progress Tracking: Project progress can be expressed in terms of percentages (%).
Limitations of Bar Charts
Lack of Detail: For large projects, only major activities can be shown, otherwise the chart becomes overcrowded and cumbersome.
No Interdependency: Bar charts do not show the dependencies or relationships between different activities.
No Critical Path: Critical activities cannot be identified, and the critical path is not determined.
Poor Controlling Tool: Progress is not clearly shown over time, making it ineffective for project control.
Uncertainty Handling: Not suitable for projects with high uncertainty in activity durations.
No Optimization: Does not allow for cost or resource optimization.
Worked Example: Drawing a Gantt Chart
Question
For a construction project, the activities and their durations are given below along with their scheduling conditions. Draw the bar chart and determine the total project completion time.
Activity
Duration (Weeks)
1
2
2
3
3
5
4
4
5
2
6
3
7
5
Precedence Conditions:
Activity 2 and 3 can be performed simultaneously and can start only when activity 1 is completed.
Activity 4 can start only after activity 2 ends.
Activity 5 cannot begin until activity 2 and 3 are complete.
Activity 6 can start only after activity 4 and 5 are completed.
Activity 7 is the last activity and can start only after the completion of activity 5.
Solution & Completion Time
By applying the precedence conditions, the activities are scheduled as follows:
Activity 1: Starts at 0, ends at week 2.
Activity 2 & 3: Start at week 2. Activity 2 ends at week 5, Activity 3 ends at week 7.
Activity 4: Starts at week 5, ends at week 9.
Activity 5: Starts at week 7 (after both 2 and 3 end), ends at week 9.
Activity 6: Starts at week 9 (after both 4 and 5 end), ends at week 12.
Activity 7: Starts at week 9 (after 5 ends), ends at week 14.
Total Project Completion Time = 14 Weeks (determined by the finish time of the last activity, Activity 7).
Your original — page 8
Solution bar chart showing the staggered scheduling of the seven activities, resulting in a 14-week project completion time.
Milestone Chart
A milestone chart is an improvement over the basic bar chart. It highlights key events or transition points (milestones) within an activity.
Milestones Defined: Key events required for the completion of an activity (represented by circles, squares, or arrows).
Advantage: Provides better detail of sub-activities, enabling better project control.
Limitation: The interdependency between various milestone events is still not clearly defined.
Linked Bar Chart
In a linked bar chart, activities are connected with arrows or lines to explicitly show their sequence, dependency, and order of execution.
Your original — page 9
Linked bar chart with dashed curved arrows representing precedence/interdependency between sequential activities.
Network Diagram
A network diagram is a graphical representation or logical model of the project plan, detailing the sequence of all activities required to complete the project.
Your original — page 10
Activity-on-Arrow (AOA) network diagram showing the logical sequence and interdependencies of events.
Network diagrams offer several key advantages:
Clearly indicates the interdependency of various activities.
Suitable for planning and managing large, complex projects.
Effective for handling uncertainty in activity durations.
Provides a strong basis for project scheduling, updating, and controlling.
Types of Network Diagrams
There are two main representations for network diagrams:
A-O-A (Activity-Over-Arrow): Activities are represented by arrows, and events/milestones by nodes.
A-O-N (Activity-Over-Node): Activities are represented by nodes, and precedence relationships by arrows.
Work Breakdown Structure (WBS)
A Work Breakdown Structure (WBS) is the process of breaking down complex project deliverables into smaller, more manageable work packages, systems, and elements.
Your original — page 11
Standard Work Breakdown Structure (WBS) hierarchy: Project → System → Subsystem → Components → Elements.
WBS is a top-down decomposition of the project scope.
Each descending level of the WBS represents an increasingly detailed definition of the project work.