CPM / Project Management

Project Management

Converted from handwritten notes — CPM 1 Project Management.pdf, pages 1 to 11

Doc No.CPM-01
StatusDraft — Awaiting Review
Converted27-07-2026
Approved—

What is a Project?

A project is a temporary endeavour undertaken to provide a unique product or service.

Objectives of a Project

Every project is managed with three primary constraints and objectives in mind:

Elements of Project Management

Planning is the most important technique of project management.

In Simple Words Work Breakdown Structure (WBS) breaks the project's physical deliverables down into smaller, manageable work packages. Organizational Breakdown Structure (OBS) maps these packages to the actual project departments or team members responsible for executing them. WBS defines what needs to be done, and OBS defines who is going to do it.

Scheduling

Scheduling is the process of establishing the sequence of activities and allocating resources (manpower, money, machine, material, space, and time) to each activity.

The 4M's of Scheduling Every project schedule must allocate and manage four key resource categories:
  • Manpower: Labour and personnel requirements.
  • Money: Financial budget and cash flow.
  • Machine: Equipment and machinery.
  • Material: Raw materials and supplies.

Controlling

Controlling is the process of monitoring project progress, identifying deviations from the plan, and taking timely corrective measures.

Planning & Scheduling vs. Controlling

There is a clear temporal distinction between planning/scheduling and controlling in project management:

Core Difference Planning and scheduling are performed before the execution of the project, whereas controlling is performed after the project has started.

Controlling relies on three key management skills:

Methods of Project Management

There are four primary methods used to plan and manage projects:

Bar Chart (Gantt Chart)

Introduced by Henry Gantt around the 1880s, a bar chart is a graphical representation of activities plotted against time.

Your original — page 4

Your original — page 4

Activity Time (days) → 2 4 5 7 8 9 11 12 Start of activity end of activity

Standard Gantt chart representing activities as horizontal bars plotted against time.

Advantages of Bar Charts

Limitations of Bar Charts

Worked Example: Drawing a Gantt Chart

Question For a construction project, the activities and their durations are given below along with their scheduling conditions. Draw the bar chart and determine the total project completion time.
Activity Duration (Weeks)
1 2
2 3
3 5
4 4
5 2
6 3
7 5
Precedence Conditions:
  • Activity 2 and 3 can be performed simultaneously and can start only when activity 1 is completed.
  • Activity 4 can start only after activity 2 ends.
  • Activity 5 cannot begin until activity 2 and 3 are complete.
  • Activity 6 can start only after activity 4 and 5 are completed.
  • Activity 7 is the last activity and can start only after the completion of activity 5.

Solution & Completion Time

By applying the precedence conditions, the activities are scheduled as follows:

Total Project Completion Time = 14 Weeks (determined by the finish time of the last activity, Activity 7).

Your original — page 8

Your original — page 8

Activities Time (weeks) → 1 2 3 4 5 6 7 2 5 7 9 12 14 14 Weeks

Solution bar chart showing the staggered scheduling of the seven activities, resulting in a 14-week project completion time.

Milestone Chart

A milestone chart is an improvement over the basic bar chart. It highlights key events or transition points (milestones) within an activity.

Linked Bar Chart

In a linked bar chart, activities are connected with arrows or lines to explicitly show their sequence, dependency, and order of execution.

Your original — page 9

Your original — page 9

Linked bar chart with dashed curved arrows representing precedence/interdependency between sequential activities.

Network Diagram

A network diagram is a graphical representation or logical model of the project plan, detailing the sequence of all activities required to complete the project.

Your original — page 10

Your original — page 10

1 2 3

Activity-on-Arrow (AOA) network diagram showing the logical sequence and interdependencies of events.

Network diagrams offer several key advantages:

Types of Network Diagrams There are two main representations for network diagrams:
  • A-O-A (Activity-Over-Arrow): Activities are represented by arrows, and events/milestones by nodes.
  • A-O-N (Activity-Over-Node): Activities are represented by nodes, and precedence relationships by arrows.

Work Breakdown Structure (WBS)

A Work Breakdown Structure (WBS) is the process of breaking down complex project deliverables into smaller, more manageable work packages, systems, and elements.

Your original — page 11

Your original — page 11

Project System Subsystem Components Elements

Standard Work Breakdown Structure (WBS) hierarchy: Project → System → Subsystem → Components → Elements.