Transportation Engineering / Highway Engineering
Hence, designing is done using edge region stress. However, checking is done for corner region. The certain combinations that are considered are:
| Case | Combination | Governing location |
|---|---|---|
| 1 — Summer & mid-day | σload,edge + σwarping,edge − σfrictional | Bottom tension + bottom tension − throughout compression (seasonal) |
| 2 — Winter & mid-day | σload,edge + σwarping,edge + σfrictional | Bottom tension + bottom tension + throughout tension (seasonal) |
| 3 — Midnight & corner | σload,corner + σwarping(night),corner | Top tension + top tension |
Generally, the 1st combination (summer & mid-day) is most critical.
Expansion joint: joint filler material inserted at the joint gap (max. 2.5 cm thickness per IRC); joint spacing designed for that gap. Maximum spacing between expansion joints is 140 m.
At expansion joints, dowels are provided — they resist bending, bearing, and shearing stress, and help in load transfer. Dowels are bonded on one side and free (able to slide) on the other.
Joint fillers are provided at the expansion joint, and it is assumed that they are compressed by 50% of their thickness. Hence, the gap of the joint should be twice the expansion in concrete.
Contraction joint: the slab is deliberately weakened at intervals so shrinkage cracks form at the predetermined location instead of randomly.
Case (a) — when no reinforcement is provided in the concrete slab, the length of contraction joint spacing is calculated as:
Where σ = permissible tensile stress in concrete. When reinforcement is not provided, maximum spacing between contraction joints is taken as 4.5 m.
f = 1.5 (coefficient of friction), γc = 2400 kg/m³ for concrete, σ = 0.8 kg/cm².
Case (b) — when reinforcement is provided, all of the tensile stress is assumed to be taken up by the reinforcing steel.
Pavement plan: longitudinal joint runs along the direction of traffic (reduces warping stress); transverse contraction and expansion joints run across the carriageway.