Transportation Engineering / Surveying
The main purpose of surveying is to plot a map of an area.
As the map is plotted on the horizontal plane, the distances shown are the horizontal projections on this plane.
In surveying, the distance between two points is the horizontal distance.
When slope distances are measured in the field, these are always reduced to the equivalent horizontal distance for the preparation of the map.
EDMI can be classified in three ways, based on the carrier wave.
| Carrier wave | Instruments |
|---|---|
| Light wave | Geodimeter, Mekometer |
| Radioactive / micro wave | Distomat, Tellurometer |
| Infrared | Total Station |
It is a branch of surveying in which distances are measured with a chain / tape — this process is called chaining. Chain surveying is used for small areas.
Chaining: the follower holds the zero end of the chain, the leader holds the forward end and drags the arrows forward; the follower then collects each arrow as the leader marks it.
In chain surveying, various points are located by measuring distances with the help of a chain or tape. For a small area, the details of various points can be collected using ties and offsets.
Left: perpendicular offset — the detail is fixed by a single measurement at right angles to the chain line. Right: oblique offset (tie) — the detail is fixed by two measured distances (ties) from two points on the chain line.
When the area is large, the error introduced due to large offsets will be more. Therefore, to overcome this difficulty, a large area is first converted into a network of triangles, and then details are noted with respect to the sides of these triangles using ties and offsets.
Main stations A, B, C, D with main survey lines AB, BC, CD, DA and base line BD; tie stations e, f joined by tie line ef; check points i, j on the base line, fixed by check lines Ai and Cj.
The measured length of the check line should be equal to the length of the check line plotted on the plan.
Chainage is measured along the direction of progress of the survey; important features (culverts, bridges) are recorded against the chainage at which they occur.
Chainage is the distance measured along the direction of progress of survey — the distance of a well-defined point from the starting point.
The term chainage is generally used in linear projects, e.g. highway, railway, sewer, canal, etc. These are used to represent important features in the work.
In chain surveying, an attempt should be made to form a triangle such that the intersection of lines is clear for plotting purposes.
The best possible well-conditioned triangle is an equilateral triangle.
Schematic — brass handles at each end, links joined by rings, tally tags fixed at every 10 links (not drawn to true link count).
| Chain | Length | Links |
|---|---|---|
| Revenue chain | 33 ft | 16 |
| Gunter's chain | 66 ft | 100 |
| Engineer's chain | 100 ft | 100 |
| Metric chain (a) | 30 m | 100 |
| Metric chain (b) | 30 m | 150 |
Page 9 lists metric chain (a) as 30 m / 100 links. The standard pairing is 20 m / 100 links and 30 m / 150 links — both give 0.2 m per link, whereas 30 m / 100 links would give 0.3 m per link, inconsistent with (b). Reproduced here exactly as written; likely "20 m" was mis-copied as "30 m." Flagged to Kishan — not silently corrected.