Linear measurement — purpose and scope

The main purpose of surveying is to plot a map of an area.

As the map is plotted on the horizontal plane, the distances shown are the horizontal projections on this plane.

In surveying, the distance between two points is the horizontal distance.

When slope distances are measured in the field, these are always reduced to the equivalent horizontal distance for the preparation of the map.

Methods of linear / horizontal measurement

EDMI — classification

EDMI can be classified in three ways, based on the carrier wave.

Carrier waveInstruments
Light waveGeodimeter, Mekometer
Radioactive / micro waveDistomat, Tellurometer
InfraredTotal Station

Chain surveying

It is a branch of surveying in which distances are measured with a chain / tape — this process is called chaining. Chain surveying is used for small areas.

A (0 m) L (20 m) follower leader

Chaining: the follower holds the zero end of the chain, the leader holds the forward end and drags the arrows forward; the follower then collects each arrow as the leader marks it.

Procedure in chain surveying

In chain surveying, various points are located by measuring distances with the help of a chain or tape. For a small area, the details of various points can be collected using ties and offsets.

free (detail) offset detail point tie

Left: perpendicular offset — the detail is fixed by a single measurement at right angles to the chain line. Right: oblique offset (tie) — the detail is fixed by two measured distances (ties) from two points on the chain line.

Note Offsets are lateral distances measured from the survey line to the station whose detail is to be collected.
  1. Perpendicular offset (simply "offset")
  2. Oblique offset ("tie")

When the area is large, the error introduced due to large offsets will be more. Therefore, to overcome this difficulty, a large area is first converted into a network of triangles, and then details are noted with respect to the sides of these triangles using ties and offsets.

Basic definitions

A B C D e f i j base line

Main stations A, B, C, D with main survey lines AB, BC, CD, DA and base line BD; tie stations e, f joined by tie line ef; check points i, j on the base line, fixed by check lines Ai and Cj.

Main station
A point where two sides of a triangle meet. These stations govern the boundary of the survey area. Ex. A, B, C, D.
Main survey line
The lines joining main stations. Ex. AB, BC, CD, DA, BD.
Tie station / subsidiary station
Stations on the line joining main stations. Ex. e and f.
Tie line / auxiliary line
Line joining tie stations. These are helpful in locating inner details of the area to be surveyed. Ex. ef.
Base line
The longest main survey line, which generally passes through the centre of the area to be surveyed. Ex. BD.
Check line / proof line
Provided to check the accuracy of field work; it is not used for plotting of any point. Ex. Ai, Cj.

The measured length of the check line should be equal to the length of the check line plotted on the plan.

Chainage

Ch. 0 Ch. 1000 box culvert Ch. 3245 slab culvert Ch. 6242 minor bridge Ch. 8921 major bridge Ch. 10,000

Chainage is measured along the direction of progress of the survey; important features (culverts, bridges) are recorded against the chainage at which they occur.

Chainage is the distance measured along the direction of progress of survey — the distance of a well-defined point from the starting point.

The term chainage is generally used in linear projects, e.g. highway, railway, sewer, canal, etc. These are used to represent important features in the work.

Well-conditioned triangle

In chain surveying, an attempt should be made to form a triangle such that the intersection of lines is clear for plotting purposes.

Intersection angle range 30°<θ<120°

The best possible well-conditioned triangle is an equilateral triangle.

Equipment used in chain surveying

Surveying chain

1 link tally (10 links)

Schematic — brass handles at each end, links joined by rings, tally tags fixed at every 10 links (not drawn to true link count).

ChainLengthLinks
Revenue chain33 ft16
Gunter's chain66 ft100
Engineer's chain100 ft100
Metric chain (a)30 m100
Metric chain (b)30 m150
⚠
Possible source slip

Page 9 lists metric chain (a) as 30 m / 100 links. The standard pairing is 20 m / 100 links and 30 m / 150 links — both give 0.2 m per link, whereas 30 m / 100 links would give 0.3 m per link, inconsistent with (b). Reproduced here exactly as written; likely "20 m" was mis-copied as "30 m." Flagged to Kishan — not silently corrected.

Unit conversions
1 ft=0.3048 m 1 mile=1.609344 km 1 mile=80× Gunter's chain 1 acre=4046.856 m2 1 acre=10×(Gunter's chain)2 1 yard=3 ft=0.9144 m