9 — Theory of Seepage

When hydraulic structures such as dams, weirs, or barrages are constructed on pervious foundations, they are subjected to seepage of water, and this seeping water exerts a force on the structure which endangers its stability and may cause failure by:

  1. Piping — the phenomenon of cavity formation below the foundation of a hydraulic structure by progressive removal of soil due to seeping water, which results in failure of the foundation due to subsidence.
  2. Direct uplift — the uplift pressure exerted by water seeping below the foundation of the structure, which leads to rupture of the structure.

Bligh's Creep Theory

H d₁ d₂ d₃ L₁ L₂ Impervious sheet pile

Bligh's creep path under a hydraulic structure with three sheet piles — percolating water is assumed to follow the outline of the base of the foundation.

L=2d1+d2+d3+L1+L2

L — creep length.

Bligh's assumptions:

Safety Against Piping

For safety against piping, sufficient creep length shall be provided to have a safe hydraulic gradient at the exit.

L=CH,   C=LH=1H/L=1safe hydraulic gradient

C — Bligh's creep coefficient. Value of C depends on the type of soil: C = 5–15; the smaller the value of C, the stronger the soil. For C = 5, soil is a mixture of coarse-grained sand and gravel.

Safety Against Uplift Pressure

For safety against uplift, the uplift water force shall be balanced by the weight of the floor of thickness t.

Gc t h' h

Balancing uplift head h' against floor of thickness t and specific gravity Gc; h = piezometric head above the top of the floor.

γwh′=Gc×γw×t t=h′Gc=h+tGc t=hGc−1
Worked Example

While designing a hydraulic structure, the piezometric head at the bottom of the floor is computed as 10 m from the datum. The datum is 3 m below the bottom of the foundation. The assumed standing water depth above the floor of the foundation is 2 m. Gc = 2.5. The floor thickness should be:

t 2 m 10 m 3 m

Datum 3 m below foundation base; piezometric head 10 m from datum; standing water 2 m above floor.

Uplift head at the bottom of the floor, measured above the floor's base level: h′ = piezometric head − depth of datum below the foundation base = 10 − 3 = 7 m. Balancing this uplift head against the downward head of standing water (2 m) plus the floor's own submerged weight (using the general balance γwh′ = Gcγwt derived above, adapted here for the standing water sitting on top of the floor):

γwh′=γwstanding water depth+γw×t×Gc 7γw=2γw+γw×t×Gc t=5Gc=52.5=2 m

t = 2 m

Worked Example

What is the floor thickness, if the datum is 3 m below the top of the floor (with the same 2 m standing water and 10 m piezometric head data as above)?

Here the datum is referenced to the top of the floor instead of its base, so the piezometric head at the top of the floor is 10 − 3 = 7 m; the uplift head at the base of the floor (a depth t further down) becomes (7 + t). Balancing this against the standing water head and the floor's submerged weight, as before:

7+tγw=2γw+tGcγw 5γw=Gc−1tγw t=51.5=3.33 m

t = 3.33 m

Lane's Creep Theory

L=2d1+d2+d3+13L1+L2

As per Lane, horizontal creep is less effective in reducing the uplift in comparison to vertical creep. Therefore he suggested a weighted factor of ⅓ to the horizontal creep, and 1 for the vertical creep.

L=CLH

CL — Lane's creep coefficient.

Khosla's Theory

According to Khosla, water does not only creep along the bottom of the floor as stated by Bligh, but instead moves along a set of stream lines. This steady seepage in the vertical plane can be expressed by Laplace's equation:

d2φdx2+d2φdy2=0

The equation represents two sets of curves — stream lines and equipotential lines — orthogonal to each other.

Khosla's Method of Independent Variables

In this method, a complex profile of a weir or barrage is broken into a number of simple profiles for which mathematical solutions were given by Khosla.

d E₁ C₁ E₂ C₂ D₁ D₂ U/S D/S B

Simple profile of a sheet-pile line with U/S pile (depth d, points E₁, C₁, D₁) and D/S pile at spacing B (points E₂, C₂, D₂).

φ=residual headtotal head×100 φD1=1πcos−11−λλ φC1=1πcos−12−λλ φD=1πcos−1λ−1λ φE=1πcos−1λ−2λ λ=1+1+α22,   α=B/d Exit hydraulic gradient (GE) =Hdπλ

Corrections in Khosla's Theory

  1. Correction for mutual interference of piles
  2. Correction for floor thickness
  3. Correction for slope of the floor
Worked Example

Determine the % pressure at various key points in the figure given below. Also determine the exit gradient, and plot the HGL for pond level on the U/S side and no flow on the D/S side.

EL 158 154 E₁ C₁ D₁ 148 E C D 144 154 57 m

U/S pile: crest 158, top of floor 154, tip 148 (d₁ = 6 m). D/S pile: floor 154, tip 144 (d₂ = 10 m). Base length B = 57 m.

For the U/S pile: using α = B/d and λ = [1 + √(1+α²)]/2 from the general formulas above:

α=576=9.5  ⇒  λ=5.276

Substituting λ into the general φD1 and φC1 formulas given above:

φD1=1πcos−11−5.2765.276=80.08% φC1=1πcos−12−5.2765.276=71.32%

Uplift pressure at D₁ = 80.08% of H = 80.08% of 4 m = 3.2 m.

For the D/S pile: using the same α and λ formulas:

α=5710=5.7  ⇒  λ=3.39

Substituting λ into the general φD and φE formulas given above:

φD=1πcos−13.39−13.39=25.07% φE=1πcos−13.39−23.39=36.52%

Using the general exit-gradient formula GE = H/(dπ√λ) given above, with the D/S pile's H = 4 m and d = 10 m:

GE=410×1π3.39×100%

φD1 = 80.08%, φC1 = 71.32%, φD = 25.07%, φE = 36.52%, exit gradient GE = 6.9%

Recap — critical tractive stress on a channel side slope For the side slope, the critical tractive stress τc′ required to move the soil particles from the side of the channel:
τc′=τc1−sin2θsin2φ

θ — the vertical angle between the horizontal and the channel side.

10 — Economics & Design of Lined Canals

Lining of a canal means that the earthen surface of the canal is protected with a stable and inerodible lining surface, such as concrete, tile, or asphalt.

Advantages of Lining

  1. Seepage loss — there are certain areas where seepage loss is of the order of 25–50%, which is a huge loss and affects the irrigation potential of the canal. By lining, seepage loss can be reduced to 2–5% of the original value.
  2. Prevention of water logging — uncontrolled seepage through an unlined canal raises the water table in adjoining areas; this phenomenon is called water logging.
  3. Increase in channel capacity — by permitting a higher velocity of flow, channel capacity is increased.
    Note V = (1/n)R2/3S1/2; n = 0.025 for an earthen channel, n = 0.015 for a concrete channel.
  4. Reduction in maintenance cost — by 40–50%. In an unlined canal, expenditure may be required on (a) periodical removal of silt deposited on the sides and bed of the canal, (b) minor repairs like filling of cracks, cuts, and uneven settlement, and (c) removal of weeds.
  5. Elimination of flood danger — in a normal earthen canal, breaching may take place, which may lead to flood/soil erosion.
  6. Increase in command area.

Disadvantages of Lining

  1. Large initial investment, which is about 2–2.5 times more than an earthen canal.
  2. Greater construction period.

Economic Justification of Lining of Canal

If the average annual benefit is greater than the average annual investment cost, then lining of the canal is justified.

Average annual benefit — monetary benefits are achieved in two ways:

  1. By reducing seepage. Let m cumec of water be saved per year, which can be sold to farmers at their rate of R₁ per cumec:
    annual benefit=mR1
  2. By reducing maintenance cost. Let R₂/year be the maintenance cost of the unlined canal, and P be the fraction of it saved by lining:
    annual benefit=PR2
Total annual benefit=mR1+PR2

Average annual investment cost — let C be the total investment cost required for construction of the lining, with design life y years.

Worked Example

An unlined canal giving a seepage of 3.3 cumec/million sq m of wetted area is proposed to be lined with 10 cm thick cement concrete lining, at cost ₹180/cu m. Given the following data, work out the economics of lining and the benefit–cost ratio: annual revenue from all crops/cumec of water = ₹3.5 lakh; discharge in channel = 83.5 cumec; area of channel = 40.8 m²; wetted perimeter of channel = 18.8 m; wetted perimeter of lining = 18.5 m; annual maintenance cost of unlined canal per 10 m² = ₹1; assume any suitable data if required.

Seepage = 3.3 cumec/10⁶ m². Consider 1 km length of canal.

Benefit from seepage: seepage loss (cumec) = seepage rate (cumec per 10⁶ m²) × wetted perimeter (m) × canal length (m) / 10⁶. For the unlined canal, with wetted perimeter 18.8 m over 1 km:

Seepage loss (unlined)=3.3×18.8×1000106=0.062 cumec

Assuming a seepage loss of 2% of the unlined-canal rate for the lined canal (using the lining's own wetted perimeter, 18.8 m; interest/depreciation taken at 4–7.25%):

Seepage loss (lined)=0.02×3.3×103×18.8106=1.24×10−3 cumec

Benefit from seepage saved, at the given rate of ₹3.5 lakh per cumec (using the general form: annual benefit = m×R₁, where m = cumec saved):

mR1=3500000.062−1.22×10−3=₹21266

Benefit from maintenance saved — general form PR₂, with the unlined-canal maintenance rate given as ₹1 per 10 m² of wetted area, over the 18.8 m × 1000 m wetted surface, and assuming a 40% saving fraction P:

PR2=0.4×18.8×1000×110=₹752

Total annual benefit = mR₁ + PR₂:

Total annual benefit=21266+752≈₹22024

Annual investment cost: total investment C = (lining quantity) × (rate per unit), using the lining's wetted perimeter 18.5 m over 1 km at ₹180 per 10 cm-thick m³:

C=18.5×103×18010=₹333000

With design life y = 40 years, average annual investment = C/y:

Cy=33300040=₹8325

Assuming a 5% rate of interest, interest lost on the average outstanding capital (C×i/2):

Interest lost=333000×0.052=₹8325 Total annual investment cost=Cy+interest lost=8325+8325=₹16650

Benefit–cost ratio = total annual benefit / total annual investment cost:

Benefit–cost ratio=2202416650=1.323>1

Benefit–cost ratio = 1.323 > 1 ⇒ lining is economically justified.

Lined Channel Cross-Sections

Generally, two types of channel cross-section are designed:

  1. Triangular section (Q < 50 m³/sec)
  2. Trapezoidal section (Q > 50 m³/sec)

Corners of the channel section are rounded to avoid silting.

y y 2θ θ

Triangular section, semi-angle θ, depth y, with rounded invert.

A=πy2×2θ2π+2×12xyycotθ=y2θ+y2cotθ=y2θ+cotθ P=2ycotθ+2yθ=2yθ+cotθ R=AP=y2
B B ycotθ y ycotθ

Trapezoidal section, bed width B, depth y, rounded side transitions.

A=By+y2θ+cotθ P=B+2yθ+cotθ R=A/P

Maximum Permissible Velocity in a Lined Canal

Type of liningPermissible velocity
Cement concrete2–2.5 m/s
Burnt clay tile1.8 m/s
Boulder1.5 m/s

Free Board in a Lined Canal

DischargeFree board
Q > 10 m³/sec0.75 m
5 – 10 m³/sec0.60 m
1 – 5 m³/sec0.50 m
< 1 m³/sec0.30 m
< 0.08 m³/sec0.10–0.15 m
Worked Example

Design a lined channel to carry a discharge of 15 m³/sec. S = 1/9000, n = 0.015. Assume a suitable value of side slope.

As discharge < 50 m³/sec, we will design a triangular section. Assume side slope 1.5H:1V:

θ=tan−111.5=33.69°=0.588 rad A=y20.588+1.5=2.088y2 P=2y0.588+1.5=4.176y
15=10.015y22/3190001/2×2.088y2

y = 2.843 m

Provide free board = 0.75 m:

design depth=2.85+0.75=3.60 m

11 — Sub-Surface (Tile) Drainage

For drain spacing: tile drains laid at some depth below ground level, above an impervious stratum, intercept the rising ground water table.

GL GWT S D a b Impervious stratum

Drain spacing geometry — two tile drains at centre-to-centre spacing S, depth D below GL, height a above the impervious stratum, with the water table drawn down to height b at midspan.

S=4Kqb2−a2
D — depth of tile drain
S — centre-to-centre spacing between tile drains
K — coefficient of permeability of soil
b — maximum height of drained water table from the impervious stratum
a — height of tile drain (centre) from the impervious stratum
Worked Example

In a tile drainage system, the drains are laid with their centre 1.5 m below the ground level. Impervious layer is 9 m below the ground, and average annual rainfall is 80 cm. If 1% of average annual rainfall is to be drained in 24 hours, to keep the highest position of the water table 1 m below ground level, find the spacing of the drain. K = 10⁻³ cm/s.

a = 9 − 1.5 = 7.5 m, b = 9 − 1 = 8 m.

Drainage coefficient q (rate to be drained, in m/s) = (fraction to be drained × annual rainfall, converted to metres/day) ⁄ (seconds per day):

q=fraction×annual rainfallseconds per day=0.01×0.8 m×102 cm/m×18.64×104 s/day

Applying the general spacing formula S = (4K/q)(b²−a²) given above, with K = 10⁻³ cm/s = 10⁻&sup5; m/s:

S=4Kqb2−a2=4×10−3×82−7.52×8.64×1040.01×0.8×100×1

S = 57.86 m

Worked Example

Find the size of the outlet of a 6 ha drainage system, if the drainage coefficient is 1 cm and the tile grade is 0.3%, and Manning's n = 0.011.

Discharge to be carried, q (m³/s) = (drainage coefficient, in m × drained area, in m²) ⁄ (seconds per day), with the 6 ha area converted to 6×10⁴ m²:

q=drainage coefficient×areaseconds per day=0.01×6×1048.64×104=6.94×10−3 m³/s

Using Manning's equation, q = (1/n)AR2/3S1/2, for a circular pipe flowing full (d = pipe diameter, A = πd²/4, R = d/4):

q=1n×π4d2×d42/3S1/2 6.94×10−3=10.011×π4d2×d42/30.31001/2

d = 0.131 m