Hydrology / Irrigation / Part 8
When hydraulic structures such as dams, weirs, or barrages are constructed on pervious foundations, they are subjected to seepage of water, and this seeping water exerts a force on the structure which endangers its stability and may cause failure by:
Bligh's creep path under a hydraulic structure with three sheet piles — percolating water is assumed to follow the outline of the base of the foundation.
L — creep length.
Bligh's assumptions:
For safety against piping, sufficient creep length shall be provided to have a safe hydraulic gradient at the exit.
C — Bligh's creep coefficient. Value of C depends on the type of soil: C = 5–15; the smaller the value of C, the stronger the soil. For C = 5, soil is a mixture of coarse-grained sand and gravel.
For safety against uplift, the uplift water force shall be balanced by the weight of the floor of thickness t.
Balancing uplift head h' against floor of thickness t and specific gravity Gc; h = piezometric head above the top of the floor.
While designing a hydraulic structure, the piezometric head at the bottom of the floor is computed as 10 m from the datum. The datum is 3 m below the bottom of the foundation. The assumed standing water depth above the floor of the foundation is 2 m. Gc = 2.5. The floor thickness should be:
Datum 3 m below foundation base; piezometric head 10 m from datum; standing water 2 m above floor.
Uplift head at the bottom of the floor, measured above the floor's base level: h′ = piezometric head − depth of datum below the foundation base = 10 − 3 = 7 m. Balancing this uplift head against the downward head of standing water (2 m) plus the floor's own submerged weight (using the general balance γwh′ = Gcγwt derived above, adapted here for the standing water sitting on top of the floor):
t = 2 m
What is the floor thickness, if the datum is 3 m below the top of the floor (with the same 2 m standing water and 10 m piezometric head data as above)?
Here the datum is referenced to the top of the floor instead of its base, so the piezometric head at the top of the floor is 10 − 3 = 7 m; the uplift head at the base of the floor (a depth t further down) becomes (7 + t). Balancing this against the standing water head and the floor's submerged weight, as before:
t = 3.33 m
As per Lane, horizontal creep is less effective in reducing the uplift in comparison to vertical creep. Therefore he suggested a weighted factor of ⅓ to the horizontal creep, and 1 for the vertical creep.
CL — Lane's creep coefficient.
According to Khosla, water does not only creep along the bottom of the floor as stated by Bligh, but instead moves along a set of stream lines. This steady seepage in the vertical plane can be expressed by Laplace's equation:
The equation represents two sets of curves — stream lines and equipotential lines — orthogonal to each other.
In this method, a complex profile of a weir or barrage is broken into a number of simple profiles for which mathematical solutions were given by Khosla.
Simple profile of a sheet-pile line with U/S pile (depth d, points E₁, C₁, D₁) and D/S pile at spacing B (points E₂, C₂, D₂).
Determine the % pressure at various key points in the figure given below. Also determine the exit gradient, and plot the HGL for pond level on the U/S side and no flow on the D/S side.
U/S pile: crest 158, top of floor 154, tip 148 (d₁ = 6 m). D/S pile: floor 154, tip 144 (d₂ = 10 m). Base length B = 57 m.
For the U/S pile: using α = B/d and λ = [1 + √(1+α²)]/2 from the general formulas above:
Substituting λ into the general φD1 and φC1 formulas given above:
Uplift pressure at D₁ = 80.08% of H = 80.08% of 4 m = 3.2 m.
For the D/S pile: using the same α and λ formulas:
Substituting λ into the general φD and φE formulas given above:
Using the general exit-gradient formula GE = H/(dπ√λ) given above, with the D/S pile's H = 4 m and d = 10 m:
φD1 = 80.08%, φC1 = 71.32%, φD = 25.07%, φE = 36.52%, exit gradient GE = 6.9%
θ — the vertical angle between the horizontal and the channel side.
Lining of a canal means that the earthen surface of the canal is protected with a stable and inerodible lining surface, such as concrete, tile, or asphalt.
If the average annual benefit is greater than the average annual investment cost, then lining of the canal is justified.
Average annual benefit — monetary benefits are achieved in two ways:
Average annual investment cost — let C be the total investment cost required for construction of the lining, with design life y years.
An unlined canal giving a seepage of 3.3 cumec/million sq m of wetted area is proposed to be lined with 10 cm thick cement concrete lining, at cost ₹180/cu m. Given the following data, work out the economics of lining and the benefit–cost ratio: annual revenue from all crops/cumec of water = ₹3.5 lakh; discharge in channel = 83.5 cumec; area of channel = 40.8 m²; wetted perimeter of channel = 18.8 m; wetted perimeter of lining = 18.5 m; annual maintenance cost of unlined canal per 10 m² = ₹1; assume any suitable data if required.
Seepage = 3.3 cumec/10⁶ m². Consider 1 km length of canal.
Benefit from seepage: seepage loss (cumec) = seepage rate (cumec per 10⁶ m²) × wetted perimeter (m) × canal length (m) / 10⁶. For the unlined canal, with wetted perimeter 18.8 m over 1 km:
Assuming a seepage loss of 2% of the unlined-canal rate for the lined canal (using the lining's own wetted perimeter, 18.8 m; interest/depreciation taken at 4–7.25%):
Benefit from seepage saved, at the given rate of ₹3.5 lakh per cumec (using the general form: annual benefit = m×R₁, where m = cumec saved):
Benefit from maintenance saved — general form PR₂, with the unlined-canal maintenance rate given as ₹1 per 10 m² of wetted area, over the 18.8 m × 1000 m wetted surface, and assuming a 40% saving fraction P:
Total annual benefit = mR₁ + PR₂:
Annual investment cost: total investment C = (lining quantity) × (rate per unit), using the lining's wetted perimeter 18.5 m over 1 km at ₹180 per 10 cm-thick m³:
With design life y = 40 years, average annual investment = C/y:
Assuming a 5% rate of interest, interest lost on the average outstanding capital (C×i/2):
Benefit–cost ratio = total annual benefit / total annual investment cost:
Benefit–cost ratio = 1.323 > 1 ⇒ lining is economically justified.
Generally, two types of channel cross-section are designed:
Corners of the channel section are rounded to avoid silting.
Triangular section, semi-angle θ, depth y, with rounded invert.
Trapezoidal section, bed width B, depth y, rounded side transitions.
| Type of lining | Permissible velocity |
|---|---|
| Cement concrete | 2–2.5 m/s |
| Burnt clay tile | 1.8 m/s |
| Boulder | 1.5 m/s |
| Discharge | Free board |
|---|---|
| Q > 10 m³/sec | 0.75 m |
| 5 – 10 m³/sec | 0.60 m |
| 1 – 5 m³/sec | 0.50 m |
| < 1 m³/sec | 0.30 m |
| < 0.08 m³/sec | 0.10–0.15 m |
Design a lined channel to carry a discharge of 15 m³/sec. S = 1/9000, n = 0.015. Assume a suitable value of side slope.
As discharge < 50 m³/sec, we will design a triangular section. Assume side slope 1.5H:1V:
y = 2.843 m
Provide free board = 0.75 m:
For drain spacing: tile drains laid at some depth below ground level, above an impervious stratum, intercept the rising ground water table.
Drain spacing geometry — two tile drains at centre-to-centre spacing S, depth D below GL, height a above the impervious stratum, with the water table drawn down to height b at midspan.
In a tile drainage system, the drains are laid with their centre 1.5 m below the ground level. Impervious layer is 9 m below the ground, and average annual rainfall is 80 cm. If 1% of average annual rainfall is to be drained in 24 hours, to keep the highest position of the water table 1 m below ground level, find the spacing of the drain. K = 10⁻³ cm/s.
a = 9 − 1.5 = 7.5 m, b = 9 − 1 = 8 m.
Drainage coefficient q (rate to be drained, in m/s) = (fraction to be drained × annual rainfall, converted to metres/day) ⁄ (seconds per day):
Applying the general spacing formula S = (4K/q)(b²−a²) given above, with K = 10⁻³ cm/s = 10⁻&sup5; m/s:
S = 57.86 m
Find the size of the outlet of a 6 ha drainage system, if the drainage coefficient is 1 cm and the tile grade is 0.3%, and Manning's n = 0.011.
Discharge to be carried, q (m³/s) = (drainage coefficient, in m × drained area, in m²) ⁄ (seconds per day), with the 6 ha area converted to 6×10⁴ m²:
Using Manning's equation, q = (1/n)AR2/3S1/2, for a circular pipe flowing full (d = pipe diameter, A = πd²/4, R = d/4):
d = 0.131 m