Geotechnical Engineering / Soil Mechanics
γsat = 18 kN/m³, γw = 9.81 kN/m³. Point Q is 2 m below the top of the soil and a standpipe piezometer reads a water level offset of 50 mm above the outer water surface at Q's location; point R is a further 0.5 m below Q, at the impermeable base.
Standpipe geometry (dimensions per the source page): 100 mm top rim, a 50 mm piezometer-tube offset, 2 m down to P, then 0.5 m each to Q and R.
The "z·&gammasub − i·z·&gammaw" shortcut from GEO-11 does not apply here, because the complete soil is not submerged (there is a dry/partial zone at the top before the piezometer's water level begins) — the shortcut assumes a fully submerged column between the datum and the point. When that assumption fails, always fall back to &sigmā = σ − u computed directly, as done above.
Flownet around a sheet pile, γsat = 20 kN/m³, γw = 10 kN/m³. Head causing flow H = 14 m, lost over Nd = 7 equipotential drops. Find effective stress at A (2 drops from upstream) and B (near the downstream toe, where pB/γw = 9 is given directly).
Flownet with 7 equipotential drops between upstream and downstream; A sits 2 drops in from upstream, B near the exit where pB/γw = 9 is read directly.
Loss up to A (2 drops) = 2×2 = 4 m. Difference of water level in piezometers at A and the upstream point C equals this head loss between C and A.
γsat = 20 kN/m³, γw = 10 kN/m³, head causing flow H = 6.5 m. First find total stress at A and B (no-flow baseline), then find effective stress including the effect of flow.
The full 6.5 m head causing flow is lost across a 3.5 m length of soil (the actual flow path length):
Loss up to A (3 m along the path):
Find pore water pressure at A. Head causing flow H = 10 m, lost across a 4 m length of soil, upward flow.
4 m soil layer sandwiched between water above and below, upward flow (from bottom water into the layer and out the top); A sits 3 m into the layer from the top.
Confirmed via the energy equation between B (bottom) and A: , i.e. 4+6 = pA/γw+3+7.5, giving pA/γw = −0.5 — the same result.
Two soil layers, each 1.5 m thick: layer A (top) with KA = 0.1 cm/s, γsat,A = 20 kN/m³; layer B (bottom) with KB = 0.01 cm/s, γsat,B = 19 kN/m³. Downward flow with total head loss 4.5 m across both layers. Find effective stress at P, which sits 0.5 m into layer B.
Continuity requires the same seepage discharge through both layers; since KA > KB, the head loss concentrates in the less permeable layer B.
Continuity of flow (same discharge Q through both layers, same cross-section area A):
Combining with hLA+hLB=4.5:
Head loss up to P (0.5 m into layer B, a third of the way through it):
A 6 m thick stratum of fine sand has submerged density γsub = 11 kN/m³. Quick sand condition (QSC) occurs at a depth of 4.2 m of excavation. What depth of GWT lowering is needed to make a 5 m deep excavation safe? γw = 10 kN/m³.
6 m sand stratum; QSC observed once excavation reaches 4.2 m depth (leaving 1.8 m of sand cover), based on the downstream water table sitting at the level of excavation.
At the baseline (4.2 m excavation) condition, buoyant weight of the remaining sand cover equals the seepage force at that instant — solving for the reference depth x used in this derivation:
Cross-checked directly via total-stress/pore-pressure (using γsat = γsub + γw = 21):
Now, if the water table is lowered by y so excavation is safe to the full 5 m depth, we assume QSC just occurs at 5 m depth (remaining cover = 1 m):
Equivalently, since QSC occurs at both 4.2 m and 5 m excavation depth, the difference of total stress must equal the difference of pore pressure between the two conditions:
If FOS = 1.5 against QSC is to be available at the full 5 m depth of excavation, find the necessary lowering of the water table.
An excavation is made through 4 m coarse sand over 2 m silty clay (γsat,clay = 19 kN/m³) over an impermeable layer, with a lake maintaining 6 m of head at the sheet pile. Assuming 15% of the total head is lost by the point x–x, express effective stress at x–x in terms of D (depth of water maintained in the excavation pit), and find the minimum D to avoid boiling.
Coarse sand of thickness (4−D) between the excavation-pit water surface and the silty clay's top (x–x), with the lake maintaining 6 m of head at the sheet pile.
For no quick sand condition, &sigmāxx must be ≥ 0:
A 1.5 m layer of soil is subjected to an upward seepage head of 1.95 m. What depth of coarse sand above the soil is required to provide FOS = 1.5 against piping? Both the coarse sand and the soil have Gs = 2.67, porosity n = 30%.
Upward flow through 1.5 m of soil (seepage pressure 1.95γw given directly), overlain by a depth x of coarse sand to be found; water is assumed to rise to the top of the coarse sand (the safer-side assumption, since actual pore pressure at B isn't otherwise known).
(same for both coarse sand and soil, since both share Gs and n).